Action item: what the Architect needs to know so every request leaves the meeting with an owner and a due date.
The minutes list four action items: cover the slope, update the site logistics plan, identify a subcontractor, send the layout survey. None names the company expected; two have no date. At the next meeting nobody can say whether anything is late. An action item is only useful if it says who acts and by when.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Tracking status | Construction | Architect, Contractor, subcontractors, Owner | High | Schedule, traceability | Action item log, “Old business” and “New business” |
1. Definition and common mistake
An action item is a line in the minutes that asks a named party to do something by a set date: send a document, make a decision, correct a condition. It differs from an info item, which records something without asking for anything, and from a follow-up, which flags a request already made and not done.
It's an industry usage term, defined by no AIA document. Section 01 31 19 usually requires the minutes to list action items and responsibilities. The item creates nothing by itself: if it goes unanswered, it is the dated record of the request, then the notice provided by the Contract, that opens the next steps (for example, the Owner's right to carry out the Work after notice under A201-2017 §2.5).
Common mistake: marking everything as an action item. If every line is urgent, none is, and readers don't know what to do first.
2. When it appears
In the action item log, by trade or by party, with columns for item number, description, ball in court, due date and status. Action items often target a document that holds up the next step, a decision before a phase starts, or a safety condition. Some minutes use “To do”, “Urgent” or color codes instead.
Typical wording: “Item 9.04, layout survey of the shoring wall: Contractor, by 03/14.” “Item 9.07, update the site logistics plan after crane relocation: Contractor, before Meeting 10.”
3. How to read it in the minutes
If you read an action item with no company → ask who is expected; an item with no owner gets no follow-up.
If you read no due date → “next meeting” becomes the due date: write it down.
If the same item comes back at the next meeting → mark it as a follow-up and keep its number.
If the item concerns safety → tell the Contractor's safety lead in writing too; the minutes don't replace the Contractor's safety program.
4. Who does what
Party | What the action item means to them | What they do |
|---|---|---|
Architect | A request to track | Name the owner, set the date, check at the next meeting |
Contractor | A response due | Act, confirm in writing with the date |
Owner | A decision it may owe | Decide, or delegate in writing |
Subcontractors | Work assigned through the Contractor | Report back through the Contractor |
5. What it changes in practice
An Architect who keeps action items for real requests gets fast answers and short minutes. One who uses them everywhere loses the signal and can't show that a given request was a priority.
Failure scenario: “Identify the shoring subcontractor” stays open for three weeks with no date and no follow-up number. The subcontractor starts without the Owner's review. After an incident, nothing in the minutes shows when the request was made or who had to answer it.
6. Typical wording
“Item 9.04, layout survey of the shoring wall: due 03/14. Ball in court: Contractor.”
“Item 9.07, revised site logistics plan: due before Meeting 10. Ball in court: Contractor.”
7. What to watch
Always name the company or party expected.
Give a date, even a short one.
Carry an unanswered item forward as a numbered follow-up.
Keep the number of action items per meeting short.
Put any safety item in writing to the Contractor as well.
8. Don't confuse with
Related term | Key difference |
|---|---|
Info item | Recorded without asking for anything |
Follow-up item | A request already made and not done |
Closed item | Done, with its closing date |
Ball in court | The status that names who acts next |
9. Related terms
Same phase (construction): Follow-up item · Info item · Closed items · Ball in court
Same party (Architect): OAC meeting · Construction scheduling · Change Order · Liquidated damages
<-