Closed items: what the Architect needs to know so the minutes get shorter without losing what was settled.
The minutes are 28 pages long. Two thirds of the items were settled months ago but still appear every week. Readers skip pages and miss the two new urgent items. Closing items, with a date, is how the minutes stay readable and keep the record.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Tracking status | Construction | Architect, Contractor, Owner | Medium | Readability, traceability | Status column, closed items log |
1. Definition and common mistake
A closed item is one whose action is done or no longer needed. It is marked closed with its closing date and, ideally, a short reason: document received, work completed, decision made. It appears once as closed, then leaves the active minutes and moves to a log or archive.
It's an industry usage term. Closing an item doesn't waive anything; it records that the action was completed. Items with contract consequences (changes, claims, notices) close only when the related instrument is issued.
Common mistake: deleting items without recording when and why they closed. Months later, nobody can show what happened.
2. When it appears
Each meeting, as items are completed, and in periodic clean-ups. Variants: “Closed”, “Complete”, “Done”, “Removed from minutes”.
Typical wording: “Item 7.12, layout survey: received 03/14. Closed.” “Items 4.01 to 4.09 closed and moved to the closed items log.”
3. How to read it in the minutes
If an item disappears without being marked closed → ask for its closing date.
If a change item is closed → check the Change Order number.
If a party disagrees with a closing → record its position and reopen if needed.
If the minutes keep growing → propose a clean-up of closed items.
4. Who does what
Party | What closing means to them | What they do |
|---|---|---|
Architect | Readable minutes | Close with dates, keep the log |
Contractor | Recognition of completion | Report completion in writing |
Owner | Confirmation | Object if not satisfied |
5. What it changes in practice
Minutes that close items regularly stay short and focused. Minutes that don't become unreadable, and important items get lost.
Failure scenario: an item is quietly deleted. At closeout, the Owner says the work was never done; nobody can show when or why it was closed.
6. Typical wording
“Item 9.04 closed 03/14: survey received.”
“Closed items log updated, 26 items. Available on request.”
7. What to watch
Mark each closing with a date and reason.
Keep a closed items log.
Close contract-related items only with the instrument.
Let parties object to a closing.
Clean up minutes regularly.
8. Don't confuse with
Related term | Key difference |
|---|---|
Info item | Still open for information |
Follow-up item | Still open and late |
Punch list closeout | Physical work verified |
Change Order | Closes a change item |
9. Related terms
Same phase (construction): Action item · Info item · Follow-up item · Purpose of meeting minutes
Same party (Architect): OAC meeting · Ball in court · Closeout submittals · Changes in the Work
<-
BACK TO FULL GLOSSARY