Commissioning

Commissioning: what the Architect needs to know so systems are proven to work before the Owner moves in.

The HVAC is installed, startup reports are signed, and the Contractor wants Substantial Completion. The commissioning authority hasn't run functional tests: the BAS isn't finished and two air handlers have open issues. Commissioning is the step that shows whether the building works, not just whether it was installed.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Quality process

Design to occupancy

Commissioning authority, Contractor, MEP trades, Architect, engineers, Owner

High

Performance, schedule

Commissioning section, MEP items

1. Definition and common mistake

Commissioning (Cx) is a quality process that verifies building systems are designed, installed, tested and able to operate as the Owner's Project Requirements (OPR) define. A commissioning authority (CxA), often hired by the Owner, writes the Cx plan, reviews submittals, checks installation, witnesses functional tests and keeps an issues log.

Energy codes (ASHRAE 90.1, IECC) require commissioning for many buildings; LEED makes it a prerequisite. ASHRAE Guideline 0 and Standard 202 describe the process. Specifications usually cover it in Section 01 91 13 and in the MEP divisions.

Common mistake: confusing startup with commissioning. Startup shows equipment runs; commissioning shows the system does what the Owner needs.

2. When it appears

From design review onward, then in a commissioning section near the end: prefunctional checklists, functional tests, issues log, trend data, training, seasonal tests. Variants: Cx, CxA, functional performance testing.

Typical wording: “Functional tests AHU-1 to AHU-4: 10/14 with the CxA. Prerequisite: BAS points complete.” “Cx issues log: 18 open, 6 critical.”

3. How to read it in the minutes

If startup is called commissioning → ask whether functional tests were done.

If critical issues stay open → check their effect on Substantial Completion.

If the BAS isn't ready → functional tests will slip.

If seasonal tests are deferred → record them with dates after occupancy.

4. Who does what

Party

What commissioning means to them

What they do

Commissioning authority

Its process

Plan, witness, report issues

Contractor and MEP trades

Systems to prove

Complete checklists, fix issues

Architect / engineers

Design intent

Answer design issues

Owner

Systems to operate

Define the OPR, attend training

5. What it changes in practice

Commissioning tracked from the start ends with a building that works on day one. Commissioning left to the end becomes a long issues log after occupancy.

Failure scenario: functional tests are skipped to meet the date. The first winter, half the zones overheat; the issues are fixed under warranty over six months.

6. Typical wording

“Cx issues log rev. 6: 12 open, 2 critical (AHU-2 economizer, BAS alarm routing). Ball in court: Mechanical subcontractor through the Contractor.”

“Seasonal cooling tests deferred to June. Info.”

7. What to watch

  • Bring the CxA in during design.

  • Separate startup from functional testing.

  • Track the issues log every meeting.

  • Link test dates to BAS completion.

  • Plan seasonal tests and training.

8. Don't confuse with

Related term

Key difference

Startup

Equipment runs, first step only

Testing and balancing

Airflow and water flow adjustment

Special inspection

Code-required, mostly structural

Punch list

Defects in finished work

9. Related terms