Design phases: what the Architect needs to know so each decision lands in the right phase.
Design meeting #5, design development. The Owner asks to move the main stair. Nobody writes that schematic design was approved two months ago. At the 50% CD estimate, the cost consultant finds a gap no one can explain. A decision does not cost the same in every phase.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Stages of the design contract | SD through CDs | Owner, Architect, consultants, cost estimator, code consultant | Cost and time of late changes | Freeze one phase before starting the next | Header, decisions, milestones |
1. Definition and common mistake
Basic services under AIA B101–2017 run in five phases: schematic design (SD), design development (DD), construction documents (CDs), procurement (formerly bidding or negotiation) and construction. Each design phase ends with a submission the Owner approves before the next one starts, usually with an updated estimate of the Cost of the Work.
Phase | What it settles | Typical deliverable |
|---|---|---|
Schematic design (SD) | Site plan, massing, program fit, major systems | Plans, sections, narrative, SD estimate |
Design development (DD) | Systems sized, materials and assemblies chosen | Drawings and outline specifications, DD estimate |
Construction documents (CDs) | Everything needed to bid, permit and build | Drawings and Project Manual |
Procurement | Bids or negotiation, addenda, award | Bid documents, addenda, conformed set |
Common mistake: thinking a phase ends when the calendar says so. It ends when the Owner approves it, in writing. A change requested after approval means redesign, and the estimate approved at that phase moves with it.
2. When it appears
The phase shows up in the header of design minutes ("Phase: DD"), in milestones ("SD submission on…") and in items deferred to later ("to be addressed in CDs"). Common variants: "50% CDs", "DD set", "permit set", "IFC" (issued for construction).
"DD submission 04/14. Owner comments on the restrooms will be addressed in CDs, at no change to the approved layout."
"Mechanical engineer keeps the SD loads; only the boiler room location changes."
3. How to read it in the minutes
If you read "to be resolved in CDs" → the decision is deferred: check that it appears on the action list with a date.
If you read "SD approved" → ask by whom and on what date: that approval is the baseline for every later change.
If you read "back to SD" → the program changed: schedule and fees are affected.
If you read "bid set" → these documents will be priced: drawings, specifications and bid form must agree.
4. Who does what
Party | What it means to them | What they do |
|---|---|---|
Owner | Each approval locks a set of choices | Approves each phase in writing, with a date |
Architect | It presents each phase and keeps the baseline | Records approvals and flags late changes with their cost |
Consultants | Their design follows the approved phase | Confirm loads, sizes and systems at each submission |
Cost estimator | Each phase has an estimate to compare | Updates the estimate and explains the variance |
5. What it changes in practice
Minutes that state the current phase, and what is already approved, keep closed choices closed. Failure scenario: an Owner request noted as "under study" during DD is never answered. It reappears at 90% CDs, after the structure is drawn. Redesign costs four weeks and an additional services request nobody expected.
6. Typical wording
"SD approved by the Owner on 02/03, subject to the geotechnical report. Next step: DD submission 04/14."
"The mass timber option requested today would mean returning to SD: impact on fees and schedule to be priced before any decision."
7. What to watch
Write the current phase in the header of every set of minutes.
Record the date and the person behind each phase approval.
Tie every request to the phase where it will be handled.
Price the impact of a late change before accepting it.
Check that code review comments follow the phases.
Don't issue the bid set on CDs the Owner hasn't approved.
8. Don't confuse with
Related term | Key difference |
|---|---|
Milestone | A date in the schedule; a phase ends with an approval |
Progress set (50%, 90%) | A check-in within a phase, not an approval |
Permit set | Documents filed with the building department, often near the end of CDs |
Delivery method | Design-bid-build, CM at risk or design-build: changes who prices when, not the design phases |
9. Related terms
Same phase (design): Drawing revision, Bid documents, Specifications, Bid form and schedule of values. Same party: Owner, Architect, Consulting engineers.