Drawing revision

Drawing revision: what the Architect needs to know so everyone works from the same version.

OAC meeting #12. The miscellaneous metals fabricator builds the guardrails from revision 2. Revision 3, issued ten days earlier, raised the handrail by 2 inches. A drawing cited without its revision is a version picked at random.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Document control

Design and construction

Architect, consultants, Contractor, subcontractors

Rework, delay

Build from the current version

Drawing log, submittals, action items

1. Definition and common mistake

A revision marks each change to a drawing or document once it has been issued. It is shown in the title block (a number or letter), with a date and a short description, and the changed area is often clouded with a delta symbol. There is no single national rule for numbering: the office standard or the Project Manual sets it, and the drawing log tracks it.

Common mistake: thinking a reviewed shop drawing stays reviewed when it changes. The review stamp applies to the revision reviewed; the next revision goes back through review.

2. When it appears

Revisions appear in the drawing log, in submittal responses ("revise and resubmit"), in ASIs and addenda, and in action items. Variants: "Rev. 3", "R3", "rev. C", "delta 4", "issued for bid", "issued for construction".

  • "Sheet A-501 reissued at Rev. 3 with ASI 014: handrail height revised; supersedes Rev. 2."

  • "Duct shop drawings Rev. 1 returned Revise and Resubmit; fabrication on hold."

3. How to read it in the minutes

  • If you read a sheet number with no revision → ask which revision: the remark may target an old one.

  • If you read "reviewed" → check which revision was reviewed, and whether a later one exists.

  • If you read "issued for construction" → that set becomes the reference on site; older ones should be marked superseded.

  • If you read "to be revised" → put it on the action list with who and when.

4. Who does what

Party

What it means to them

What they do

Architect

It controls the design documents

Issues revisions with a description and keeps the drawing log

Consultants

Their sheets change with the design

Revise, cloud and describe each change

Contractor

It must build from the current set

Distributes revisions and pulls superseded sheets from the field

Subcontractors

They fabricate from drawings

Check the revision before ordering or fabricating

5. What it changes in practice

A drawing log kept current in the minutes, with the latest revision of each sheet and who received it, prevents most "we built it from the old drawing" disputes. Failure scenario: the minutes say "guardrail drawings approved" without a revision. The fabricator builds from Rev. 2, the inspector rejects the height, and nobody can say from the minutes which version was approved.

6. Typical wording

"Drawing log: S-201 at Rev. 4 (ASI 017, beam size at grid C). Rev. 3 superseded. Contractor to confirm field set updated by 03/12."

"Storefront shop drawings Rev. 2: reviewed with comments; Rev. 1 is void."

7. What to watch

  • Always write the revision next to the sheet or document number.

  • Describe each revision in one line: what changed and why.

  • Mark superseded sheets on site, not only in the log.

  • Send each revision to every trade it affects.

  • Re-review a submittal when it changes, even slightly.

  • Keep the drawing log in the minutes or linked from them.

8. Don't confuse with

Related term

Key difference

Issue date

When a set was sent; a revision says what changed

Addendum

Changes bid documents before award

ASI

Architect's instruction during construction, often with revised sheets

Version (file)

Internal draft; a revision is issued to others

9. Related terms

Same phase: Design phases, Bid documents, Submittal review, Specifications. Same party: Architect, Consulting engineers.

Sources: no national standard sets revision numbering; follow the Project Manual and the office's drawing standards. See AIA B101–2017 instructions (conformed and record documents).