Engineering calculations: what the Architect needs to know so nothing is built without justification.
OAC meeting #8. The helical piles are already installed. The delegated design calculations arrived the day before, sent straight to the building department, without going through the design team. Calculations get reviewed before the work, not after.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Technical justification | Design and construction | Engineers of record, delegated engineers, Architect, building official | Safety, permit | Review before installation | Submittals, deferred submittals, action items |
1. Definition and common mistake
Engineering calculations justify a design: loads, member sizes, connections, duct and pipe sizing, energy compliance. No code defines a standard format. The building code (IBC Section 107, as adopted locally) lets the building official require calculations with the construction documents. Deferred submittals, often delegated designs, are reviewed by the registered design professional in responsible charge before they go to the building official.
Common mistake: thinking the building department's approval replaces the design team's review. The building official checks code compliance; conformance with the design remains the engineer of record's review.
2. When it appears
Calculations appear with permit submittals, deferred submittals, delegated design packages and RFIs about capacity. Variants: "calcs", "structural calcs", "delegated design", "deferred submittal", "load letter", "energy compliance".
"Deferred submittal: helical pile calculations, sealed, to be reviewed by structural EOR before forwarding to the building department."
"Curtain wall anchor calcs Rev. 1 returned Revise and Resubmit: wind load per ASCE 7 not shown."
3. How to read it in the minutes
If you read "calcs submitted to the city" → check that the engineer of record reviewed them first.
If you read work started with "calcs pending" → stop and confirm: this is a hold point.
If you read "load letter" → confirm it covers the actual equipment and location.
If you read "Revise and Resubmit" → the work it supports waits for the next revision.
4. Who does what
Party | What it means to them | What they do |
|---|---|---|
Engineer of record | It sets criteria and reviews | Reviews delegated calculations for conformance with the design |
Delegated engineer | It designs one component | Prepares and seals calculations to the stated criteria |
Architect | It coordinates the review path | Routes calculations, tracks status in the minutes |
Contractor | It must not build ahead of review | Submits on time, waits for review before installing |
5. What it changes in practice
Minutes that track each calculation package, its revision and review status prevent work from getting ahead of its justification. Failure scenario: the piles go in before the calculations are reviewed; the review finds a capacity shortfall, and two piles are added after the fact.
6. Typical wording
"Helical pile calcs (delegated design) received 08/12; EOR review due 08/19. Installation on hold until reviewed."
"Rooftop unit load letter accepted by structural EOR; supports per detail 5/S-501."
7. What to watch
List every deferred submittal at the start of construction.
Route calculations through the engineer of record first.
Treat pending calculations as a hold point.
Check the revision of the calculations against the drawings.
Confirm design criteria (loads, codes) in the delegated design request.
Record review dates in the minutes.
8. Don't confuse with
Related term | Key difference |
|---|---|
Shop drawings | Show how it's built; calculations show why it holds |
Building department approval | Code compliance, not design review |
Special inspection | Verifies construction, not the design |
Product data | The manufacturer's information, not a project-specific design |
9. Related terms
Same phase: MEP coordination, Submittal review, Special inspection, Hold point. Same party: Consulting engineers, Architect.
Sources: STRUCTURE magazine, building officials' expectations · IBC Section 107 (as adopted by the jurisdiction)
Template: Design meeting minutes
<-
BACK TO FULL GLOSSARY