Hold point

Hold point: what the Architect needs to know so work doesn't proceed past a step that had to be checked.

The specification says the waterproofing must be inspected before backfill. The backfill was done on Tuesday; the inspection was planned for Thursday. Now the question is whether to dig back up. A hold point only works if everyone knows it exists and who releases it.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Quality step

Design and construction

Contractor, Architect, engineers, special inspector, commissioning authority

High

Quality, schedule

Quality section, inspections

1. Definition and common mistake

A hold point is a step where work must stop until a named party reviews or inspects it and releases it. A witness point is lighter: the party is invited but work may proceed if it doesn't come. Hold points cover concealed work (rebar before pours, waterproofing before backfill, in-wall MEP before drywall), tests and design steps (shop drawings approved before fabrication).

In US practice, hold points come from the specifications, the statement of special inspections (IBC Chapter 17) and the quality plan. Under A201-2017 §12.1, work covered contrary to the Architect's request or to requirements of the Contract Documents must be uncovered at the Contractor's expense if required.

Common mistake: listing hold points only in the specs. Without a list in the minutes, trades find out after the fact.

2. When it appears

At project start (list of hold points by trade), then in the quality section as each comes up: who releases, when, with what record. Variants: inspection hold, release point, cover-up inspection.

Typical wording: “Hold point: waterproofing inspection before backfill, west wall. Release by special inspector.” “Cover-up inspection Level 2 MEP in walls: released 05/09.”

3. How to read it in the minutes

If you read concealed work with no hold point → ask whether an inspection is required.

If a hold point has no release record → the work isn't released.

If work proceeded past a hold point → record it; uncovering may be required at the Contractor's cost.

If the releasing party is unavailable → set a date or a delegate in writing.

4. Who does what

Party

What the hold point means to them

What they do

Contractor

A step to plan

Call for inspection on time, wait for release

Releasing party

A check to perform

Inspect, release or reject in writing

Architect

Quality oversight

Keep the list, record releases

Owner

Quality assurance

Receive reports

5. What it changes in practice

A shared list with dates keeps inspections on the schedule. Without it, work gets covered and either the inspection is lost or the work is torn out.

Failure scenario: drywall closes Level 2 before the MEP cover-up inspection. The inspector refuses to sign off; 40 openings are cut and patched.

6. Typical wording

“Hold point HP-07: Level 2 in-wall MEP before drywall. Released by inspector 05/09 (report 22).”

“HP-03 waterproofing west wall: backfill done before inspection. Uncovering required. Ball in court: Contractor.”

7. What to watch

  • List hold points by trade at project start.

  • Name who releases each one.

  • Require a written release before proceeding.

  • Schedule inspections in the lookahead.

  • Record any work covered before release.

8. Don't confuse with

Related term

Key difference

Witness point

Work may proceed if no one attends

Special inspection

Code inspection, often a hold point

Mock-up

Sets a standard, not a stop

Stop-work order

An incident, not a planned step

9. Related terms

Same phase (construction): Special inspection · Mock-up · Grade beams · Submittal review

Same party (Architect / Contractor): Commissioning · Punch list · OAC meeting · Construction scheduling

<-

BACK TO FULL GLOSSARY