Info item

Info item: what the Architect needs to know so a line kept “for record” doesn't turn into a forgotten request.

The façade section of the minutes has twelve “Info” lines. Some date back to mobilization, others were settled weeks ago, two should have been action items. An info item keeps a topic in view without asking for anything now. It has to be reread at each meeting, or it clutters the minutes and hides what matters.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Tracking status

Construction

Architect, Contractor

Medium

Readability, traceability

Meeting record, status column

1. Definition and common mistake

An info item records something without asking anyone to act before the next meeting: information shared, a decision expected later, a topic to watch. It differs from an action item, which asks a named party to do something by a date, and from a follow-up, which flags a request not met.

It's an industry usage term. An info item creates no obligation and no due date; it records that a topic exists. The day something has to be done, the line changes status and names who acts.

Common mistake: letting an info item become a request without changing its status. The Contractor reads “Info” and does nothing; the Architect thinks the request was made.

2. When it appears

In the meeting record, for information shared (“revision C drawings issued”), a date far off (“commissioning in September”), a coordination topic with no action now, or an Owner decision expected later. Variants: “FYI”, “For record”, “Noted”.

Typical wording: “Window delivery expected week 22. Info.” “Owner's color selection expected in May. Info.”

3. How to read it in the minutes

If you read an info item with an action verb → it's a request in disguise: make it an action item with an owner.

If an info item is over two months old → check that it still matters; if not, close it with the date.

If an info item carries a future date → put it in the schedule so it surprises no one.

If you are the Contractor → an info item asks nothing of you, but check that it's accurate.

4. Who does what

Party

What the info item means to them

What they do

Architect

A topic to keep in view

Reread each meeting, change status when action is needed

Contractor

Information on record

Check accuracy, report errors

Owner

A decision to come

Prepare it on time

Absent readers

Project context

Read to avoid surprises

5. What it changes in practice

Minutes with few info items, reread and closed on time, stay short and readable. Minutes that pile them up reach twenty pages where the important lines get lost.

Failure scenario: “Shaft openings to be confirmed” sits as an info item for six weeks. Nobody asked anyone. The slab is poured without the openings, and core drilling costs three days.

6. Typical wording

“Special inspector visit scheduled 04/18. Info.”

“Window colors: Owner's decision expected at Meeting 15. Info.”

7. What to watch

  • Never write a request as an info item.

  • Reread info items each meeting and close the ones that no longer matter.

  • Date info items that announce an event.

  • Keep the list short.

  • Keep a record of closed info items with their dates.

8. Don't confuse with

Related term

Key difference

Action item

Request due before a set date

Follow-up item

Request not met, carried forward

Closed item

Removed from tracking, with its date

General Notes

Standing rules, not meeting information

9. Related terms

Same phase (construction): Action item · Follow-up item · Closed items · Ball in court

Same party (Architect): OAC meeting · Purpose of meeting minutes · Baseline schedule · Construction scheduling

<-