Weather delay day: what the Architect needs to know so each day is recorded once, with its data.
March, earthwork phase. It rained six days this month. The Contractor asks for six days. The specifications anticipate four rain days in March, and on two of the six the crews were pouring indoors. A weather delay day is a day the critical path stopped because conditions exceeded set thresholds. The minutes record the stoppage; the time comes by Change Order.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Time adjustment | Construction | Contractor, Architect, Owner | Medium to high | Schedule, financial | General Notes, schedule section |
1. Definition and common mistake
A weather delay day is a working day on which work on the critical path stops, or is cut below a set share of the day, because weather exceeds the thresholds in the Contract. Typical thresholds cover rain, wind, cold, snow and heat. They are measured at a named station, often a NOAA station near the site.
Under A201-2017 §15.1.6.2, a claim for time due to adverse weather must show three things. The weather was abnormal for the period, could not reasonably have been anticipated, and had an adverse effect on the scheduled construction. Many specifications add a table of anticipated weather days per month in Division 01, and only days beyond those count. On federal work, unusually severe weather is an excusable delay under FAR 52.249-10. Time is granted by Change Order, which moves the date liquidated damages start.
Common mistake: a reporting deadline invented in the minutes ("not reported within the week, not considered"). Claims follow the Contract's notice rules, and the minutes can't remove that right.
2. When it appears
It appears in Division 01 (often in the summary of work or a dedicated weather section), in the General Notes, in daily reports and in time extension requests. Variants include "rain day", "weather day", "adverse weather delay" and "inclement weather day". Typical wording:
"Rain over 0.50 in between 7 a.m. and 3:30 p.m., stoppage recorded."
"Four anticipated weather days in March, per the Specifications."
3. How to read it in the minutes
If you read a weather day with no station data → ask for the readings before recording it.
If you read a weather day on non-critical work → it doesn't extend the Contract Time.
If you read "agreed weather days: 6" → the minutes record days; time comes only by Change Order.
If you read "not reported, not considered" → delete it: the Contract's claim rules apply.
4. Who does what
Party | What a weather delay day means to them | What they do |
|---|---|---|
Contractor | Time it can claim | Reports the stoppage with station data |
Architect | A fact it records | Records the stoppage, reviews the claim |
Owner | Time it may grant | Signs the Change Order for time |
Subcontractors | Lost days on their work | Report to the Contractor, not to the Owner |
5. What it changes in practice
Thresholds with hours and a station make each day checkable. The minutes then record a stoppage, not an opinion. Vague thresholds ("heavy rain") turn each month into a negotiation.
Failure scenario: the minutes accept every rain day reported, with no thresholds. Over a winter the Contractor reaches 31 days. Nine were above the anticipated days, and only five fell on the critical path. The Owner signs a Change Order for 31, then argues it at closeout. The liquidated damages period shrinks by three weeks it should not have lost.
6. Typical wording
"Weather delay day 03/12: 0.82 in of rain between 7 a.m. and 3:30 p.m. at the named station, critical path earthwork stopped. Recorded; time adjusted by Change Order net of anticipated days."
7. What to watch
Write thresholds with a time window and a named station.
Count only days on the critical path.
Subtract the anticipated weather days set in the Contract for that month.
Record days in the minutes; grant time only by Change Order.
Never add a reporting deadline the Contract doesn't contain.
8. Don't confuse with
Related term | Key difference |
|---|---|
Force majeure | A broader category; weather is often one case of it |
Excusable delay | Gives time; it may not give money |
Anticipated weather days | Built into the schedule, never compensated |
Suspension of work | Ordered by the Owner, not caused by weather |