Architect

Architect: what the Architect needs to know to write what it decides, and what it only recommends.

OAC meeting #15. "The Architect accepts the plaster repair proposal." The Owner signed nothing; the Contractor started the next day. The Architect recommends, reviews and certifies; it doesn't commit the Owner's money.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Design professional

Design and construction

Architect, Owner, consultants, Contractor

Liability, authority

Write the role behind each action

Decisions, submittals, changes

1. Definition and common mistake

The Architect is the licensed design professional hired by the Owner to design the project and, usually, administer the construction contract. Under AIA B101 it provides services through design, procurement and construction; under A201 Article 4 it acts as the Owner's representative during construction, reviews submittals, interprets the documents, certifies payments and prepares changes. It coordinates its consultants, whose sealed documents form part of the set.

Common mistake: writing "the Architect accepts" or "the Architect approves" for a price or a scope change. The Architect evaluates and recommends; the Owner commits the money. What the Architect does on its own is what its contract gives it: review, interpret, order minor changes that don't affect price or time, and certify.

2. When it appears

The Architect appears in nearly every line of design minutes, and in OAC minutes for submittals, RFIs, ASIs, field reports and pay applications. Variants: "AOR" (architect of record), "A/E", "design team", "CA" (construction administration).

  • "Architect to issue ASI 019 clarifying the soffit detail; no change in cost or time."

  • "Architect reviewed Pay Application #6 and certified $412,300."

3. How to read it in the minutes

  • If you read "Architect accepts" a price → ask whether the Owner signed: if not, it's a recommendation.

  • If you read "Architect reviewed" → the review covers conformance with design intent, not the Contractor's means and methods.

  • If you read "design team" → name the firm or consultant responsible.

  • If you read "per Architect" on site → check that a written instruction exists (ASI, RFI response).

4. Who does what

Party

What it means to them

What they do

Architect

It designs and administers

Recommends, reviews, interprets, certifies, prepares changes

Owner

It relies on the Architect's advice

Decides and signs what changes price or time

Consultants

They work under the Architect

Design their systems, review related submittals

Contractor

It receives the Architect's instructions

Builds per the documents and written instructions

5. What it changes in practice

Minutes that separate "Architect recommends", "Architect reviewed" and "Owner approved" protect both the Architect and the Owner. Failure scenario: "Architect accepts" is read as an authorization. The work proceeds, and the Owner disputes the cost and the Architect's authority.

6. Typical wording

"Architect recommends accepting the plaster repair proposal ($18,600). Pending Owner approval; no work before a signed Change Order."

"Architect reviewed curtain wall shop drawings Rev. 2: no exceptions taken."

7. What to watch

  • Use "recommends" when the Owner must decide.

  • Write which firm or consultant reviewed a submittal.

  • Put every instruction that affects the Work in writing.

  • Keep reviews to design intent, not means and methods.

  • Flag any request outside the Architect's scope of services.

  • Check the stamp: who is the licensed professional of record.

8. Don't confuse with

Related term

Key difference

Owner

Decides and pays

Consulting engineers

Design their own systems under the Architect's contract

Construction manager

Manages construction for the Owner or as a contractor

Contractor

Builds; controls means and methods

9. Related terms

Same party: Owner, Consulting engineers, Submittal review. Same phase: Design phases, Drawing revision, Change Order.

Sources: AIA B101–2017 summary · AIA A201–2017, Article 4 (Architect)