Area turnover: what the Architect needs to know so each handoff between trades is dated and the condition is recorded.
The drywall contractor says Level 4 is ready for paint. The painter finds holes, missing corner beads and debris. The flooring contractor arrives the next week and finds paint on the slab. Each says the area was turned over that way. A recorded turnover, with the condition and the date, settles who fixes what.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Coordination step | Construction, closeout | Contractor, trades, Owner, Architect | Medium | Quality, schedule, cost | Trade coordination, schedule section |
1. Definition and common mistake
An area turnover is the handoff of a defined area from one trade to the next, or from the Contractor to the Owner for early use. It records the date, the condition of the area, who accepts it and what stays open.
Between trades, it is part of the Contractor's coordination: A201-2017 §3.3 makes the Contractor responsible for sequences and coordination, and §3.14 and §10.2 cover cutting, patching and damage. For Owner use before completion, §9.9 allows partial occupancy with the Contractor's consent and agreement on responsibilities.
Common mistake: turning over by phone without a walk. When damage appears, nobody can say when it happened.
2. When it appears
In trade coordination and the schedule: floor-by-floor sequences, early Owner access (fit-out, IT, furniture), partial occupancy. Variants: area release, handoff, turnover walkthrough, partial occupancy.
Typical wording: “Level 4 turned over from drywall to paint 06/03 after walk; 12 items listed.” “Owner IT access to Level 2 server room from 07/01 under partial occupancy terms.”
3. How to read it in the minutes
If you read “ready” without a walk → ask for a turnover walk with both trades.
If items are open at turnover → list them with their ball in court.
If the Owner takes early access → check partial occupancy terms: insurance, utilities, damage, warranty start.
If damage appears after turnover → the date shows which trade was in the area.
4. Who does what
Party | What turnover means to them | What they do |
|---|---|---|
Contractor | Sequence and coordination | Organize walks, record condition |
Outgoing trade | Its work completed | Clean, list open items |
Incoming trade | Its starting condition | Accept or report issues |
Owner | Early use, if any | Agree terms in writing |
Architect | Record and contract advice | Record turnover, advise on §9.9 |
5. What it changes in practice
Dated turnovers with a condition list make damage disputes short. Without them, back-charges between trades eat the Contractor's time at the end.
Failure scenario: the Owner's furniture vendor enters Level 3 without a turnover. Walls are scuffed and the floor is scratched. The Contractor, the flooring trade and the vendor blame each other.
6. Typical wording
“Level 4 turnover drywall → paint 06/03, walk completed, 12 items (attached). Ball in court: Drywall subcontractor through the Contractor.”
“Level 2 server room: Owner access 07/01 under §9.9 agreement. Insurance confirmed. Info.”
7. What to watch
Walk each turnover with both parties.
Date it and list open items.
Agree partial occupancy terms in writing.
Protect finished work after turnover.
Keep photos of the condition.
8. Don't confuse with
Related term | Key difference |
|---|---|
Substantial Completion | Contract milestone for the whole Work or a portion |
Partial occupancy | Owner use before completion |
Floor release | Release of a level for next phase |
Punch list | Remaining items before final completion |
9. Related terms
Same phase (construction): Floor release · Punch list · Substantial Completion · Mock-up
Same party (Contractor / Owner): Site logistics plan · OAC meeting · Construction scheduling · Ball in court
<-
BACK TO FULL GLOSSARY