Avance forfaitaire: a French term you'll meet in French meeting minutes, with how it compares to US practice.
On a French public project, the minutes say: “Advance to the roofing trade to be repaid from the next payment applications.” A US reader may be surprised that a public owner pays before work starts. In French public contracts, it is the default.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
French public procurement | Start, construction | Public owner, contractors | Medium | Contractor cash flow | Payment section |
What it is
Under the French public procurement code, a public owner pays an advance to contractors on most public contracts above a threshold and longer than two months, as a percentage of the contract amount, unless the contractor declines it. The advance is repaid by deductions on later payments, starting at a set level of progress. A guarantee may be required.
Closest US equivalent
Mobilization payments or a mobilization line in the schedule of values, sometimes allowed in public and private contracts. Advance payments are less common on US public works, where contractors are usually paid only for work in place and stored materials.
In the minutes
The advance appears in payment items: when it is paid, when repayment starts, and its effect on each payment application.