BACK TO FULL GLOSSARY

Ball in court

Ball in court: what the Architect needs to know so every open item shows who has to act next.

An RFI has been open for 19 days. The Contractor says it is waiting on the Architect. The Architect says the question was incomplete and went back to the Contractor. Nobody wrote it down. Ball in court ends that argument. Each open item names the one party that has to act next, and the minutes record it at every meeting.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Status

Construction, closeout

All parties

High

Schedule, traceability

Action items, RFI and submittal logs

1. Definition and common mistake

Ball in court (BIC) names the party that holds the next action on an open item. That item can be an RFI, a submittal, a change proposal, a special inspection discrepancy or an action item. When that party acts, the ball moves to the next one, and the date of each move is kept. The term comes from tennis and is now standard in construction logs.

It is an industry usage term, not defined by the AIA documents. It still rests on contract deadlines that are defined. A201 §3.10.2 asks the Contractor for a submittal schedule that leaves the Architect reasonable time to review. Under A201 §4.2.7, the Architect reviews with reasonable promptness. The ball in court shows, item by item, whether those times are being kept.

Common mistake: naming two parties ("Contractor / Architect"). If two parties hold the ball, nobody does.

2. When it appears

You find it in RFI and submittal logs, in the action items of the minutes, and in closeout trackers. It may be written as "BIC", "Ball in court", "Action by" or "Responsible". Some logs add the number of days the item has spent with each party. Typical wording:

  • "Ball in court: Special Inspector."

  • "RFI 42, ball in court: Architect since 10/02."

3. How to read it in the minutes

  • If you read "Ball in court: Architect" for more than the review time → respond, or record why the item is on hold.

  • If you read a firm name with no person → that's enough for the minutes; the firm assigns internally.

  • If you read the same party for four meetings → escalate: add a due date and copy the Owner.

  • If the ball moved with no date → add the date. That date is what a delay analysis relies on.

4. Who does what

Party

What ball in court means to them

What they do

Contractor

It owns the next step on its RFIs and resubmittals

Answers or resubmits, reports the date

Architect

It owns the review step

Reviews within the agreed time, updates the log

Owner

It owns decisions and owner-furnished items

Decides, or delegates in writing

Consultants and agencies

They own their reviews and reports

Deliver, and the Architect records the date

5. What it changes in practice

With a ball in court on every line, an open item can't sit unowned. The minutes become a running record of who held up what. Without it, the log lists topics and the delay can't be assigned.

Failure scenario: a door hardware submittal is marked "pending" for six weeks. The Contractor claims the Architect held it. The Architect had returned it "revise and resubmit" on day four. Nothing in the minutes shows the ball went back to the Contractor. The Owner ends up granting time on a delay that was not its own.

6. Typical wording

"Submittal 08 71 00-02, door hardware: returned Revise and Resubmit 09/18. Ball in court: Contractor."

"DR-14, special inspection discrepancy: correction sent 09/22. Ball in court: Special Inspector."

7. What to watch

  • Put one party only in the ball in court, never two.

  • Date every move of the ball, in the log and in the minutes.

  • Use the same status labels across the RFI, submittal and action item logs.

  • Escalate any item that stays with the same party past its due date.

  • Record your own items honestly: the Architect is often the one holding the ball.

8. Don't confuse with

Related term

Key difference

Responsible party

Who is accountable for the work; the ball in court is who acts next

Due date

When the action is expected, not who must do it

Hold

The item is stopped on purpose; the reason is recorded

Action item

The line itself; ball in court is one of its fields

9. Related terms

Same phase (construction): OAC meeting, RFI, Submittal, Special inspection. Same party (Architect): Submittal review, Change Order, Punch list, Field report.

<-

BACK TO FULL GLOSSARY