Baseline schedule

Baseline schedule and look-ahead: what the Architect needs to know so each week's plan is measured against the reference.

Every meeting, the Contractor shows a three-week look-ahead. It always looks fine. Nobody compares it to the baseline, and after six months the project is eight weeks late without anyone having said so. The look-ahead says what happens next; the baseline says whether that is on time.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Schedule documents

Construction

Contractor, Architect, Owner, trades

High

Schedule

Schedule section

1. Definition and common mistake

The baseline schedule is the first complete CPM schedule accepted at the start of the job. It is the reference for measuring progress and delays. Monthly updates show progress against it. The look-ahead (usually three weeks) breaks near-term work into detail by trade and area, so crews and inspections can be coordinated.

Section 01 32 16 typically requires the baseline within a set time after Notice to Proceed, monthly updates, and short-interval schedules. Changing the baseline usually requires a Change Order or the Owner's agreement.

Common mistake: discussing only the look-ahead. Without comparing to the baseline, slippage builds up unseen.

2. When it appears

Baseline: at the start, then as reference in monthly updates. Look-ahead: every OAC meeting, by area and trade. Variants: master schedule, short-interval schedule, two- or six-week look-ahead.

Typical wording: “Look-ahead weeks 22 to 24 reviewed; L5 drywall starts week 23, 2 weeks later than baseline.” “Baseline schedule rev. 0 accepted 02/10.”

3. How to read it in the minutes

If you only see look-aheads → ask how the end date compares to the baseline.

If a look-ahead activity is later than baseline → ask whether it is critical.

If the Contractor proposes a new baseline → it needs the Owner's agreement.

If inspections appear in the look-ahead → confirm they are booked.

4. Who does what

Party

What these schedules mean to them

What they do

Contractor

Its plan and its reference

Maintain both, explain variances

Trades

Their next weeks

Commit to look-ahead activities

Architect

Contract administration

Record variances, advise

Owner

Its dates

Decide on re-baselining

5. What it changes in practice

Comparing look-ahead to baseline every month makes delays visible early, when recovery is still possible.

Failure scenario: eight months of look-aheads without baseline comparison. The delay is discovered at once, too late to recover, and turns into a claim.

6. Typical wording

“Look-ahead weeks 22–24: L5 drywall week 23 (baseline week 21). Not critical, float 6 days. Info.”

“Proposed re-baseline: pending Owner decision. Ball in court: Owner.”

7. What to watch

  • Get the baseline accepted early.

  • Compare to the baseline each month.

  • Use the look-ahead to book inspections and deliveries.

  • Treat re-baselining as a contract decision.

  • Keep each version with its date.

8. Don't confuse with

Related term

Key difference

Schedule update

Progress against the baseline

Schedule acceptance

How the baseline becomes the reference

Recovery schedule

Plan to catch up

Milestone schedule

Key dates only

9. Related terms

Same phase (construction): Construction scheduling · Schedule acceptance · Weather delay day · Liquidated damages