Benchmark: what the Architect needs to know so every trade measures from the same elevation.
The concrete subcontractor sets the slab from one mark, the curtain wall installer from another. Half an inch apart at Level 1, an inch at Level 4. Nobody knows which one is right because the original benchmark was knocked out by an excavator three weeks ago. A benchmark is only useful if it is recorded, protected and shared.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Survey reference | Site work, structure | Surveyor, Contractor, all trades, Architect | High | Technical, quality | Site work section, layout items |
1. Definition and common mistake
A benchmark is a fixed point of known elevation that all trades measure from. The civil drawings tie it to a vertical datum (often NAVD 88) or to a project datum, for example “Finished floor Level 1 = 100'-0"”. Secondary benchmarks are transferred to stable points around the site and on each floor.
Under A201-2017 §3.2.2, the Contractor checks field measurements and reports errors it finds; layout is the Contractor's responsibility unless the Contract says otherwise. The Owner usually provides the property survey and the original control points (§2.3.4).
Common mistake: letting each trade set its own reference. Small differences add up and show at interfaces: doors, elevators, façades.
2. When it appears
At mobilization (control points turned over, initial survey), at each structural level (transfer of benchmarks), and when a reference is damaged or questioned. Variants: control point, datum, “BM”, project zero.
Typical wording: “Benchmark BM-2 on the east property line destroyed; new point set by the surveyor 03/04.” “Level 3 benchmark transferred and verified, elevation 124'-6".”
3. How to read it in the minutes
If you read a damaged benchmark → ask when it was reset and by whom, and whether recent work was checked.
If two trades disagree on an elevation → go back to the primary benchmark before discussing who is wrong.
If the project datum and the civil datum are mixed → write the conversion once in the General Notes.
If an elevator or façade installer arrives → confirm which benchmark it will use.
4. Who does what
Party | What the benchmark means to them | What they do |
|---|---|---|
Surveyor | The reference to set and certify | Set, transfer, issue a survey record |
Contractor | Layout responsibility | Protect points, give them to all trades |
Trades | The elevation to work from | Use only the shared benchmark |
Architect | Design intent | Check consistency with the drawings |
5. What it changes in practice
A recorded and protected benchmark keeps interfaces aligned. A lost or doubled reference shows up late, when a door won't close or a façade joint opens.
Failure scenario: the benchmark is reset after damage, without a survey record. The second reference is a half inch off. Two floors of partitions are set from it before the elevator installer finds the gap.
6. Typical wording
“BM-1 destroyed 03/02. New BM-1A set by surveyor, elevation 100'-0", survey record issued 03/04. Ball in court: Contractor to distribute.”
“Level 4 benchmark transferred and checked against BM-1A. Info.”
7. What to watch
Record each benchmark with its location and elevation.
Protect points from equipment traffic.
Ask for a survey record whenever a point is reset.
Give the same reference to every trade.
State the project datum in the General Notes.
8. Don't confuse with
Related term | Key difference |
|---|---|
Control point | Horizontal and vertical position, not only elevation |
Gridlines | Horizontal layout reference |
Finished floor elevation | A design value, not a field mark |
As-built survey | Measures what was built |
9. Related terms
Same phase (site work): Hydraulic breaker · Grade beams · Site logistics plan · Floor release
Same party (Contractor / surveyor): Special inspection · Closeout submittals · OAC meeting · Construction scheduling
<-
BACK TO FULL GLOSSARY