Bid documents: what the Architect needs to know about which version governs.

OAC meeting #14. The plumber sets a manhole at the bike room, as shown in the bid set. The conformed drawing, Rev. 3, moved it six feet after bid negotiations. The bid documents describe what was priced; the contract describes what was signed.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Procurement documents

Procurement, then construction

Owner, Architect, bidders, Contractor

Price, scope

Know which version governs

Bid milestones, addenda, conformed set

1. Definition and common mistake

The bidding documents are what bidders receive to price the project. Under AIA A701–2018 they include the bidding requirements (invitation to bid, instructions to bidders, bid form) and the proposed Contract Documents (agreement, conditions, drawings, specifications), plus all addenda. After award, the Contract Documents govern; a conformed set incorporates the addenda and accepted alternates.

Common mistake: citing "the bid set" on site as the contract reference. After award, the executed Contract Documents govern. The bid set explains where a difference comes from; it doesn't settle it.

2. When it appears

The term appears in design minutes as a milestone ("bid set issued 03/02"), during bidding (pre-bid meeting, questions, addenda) and on site when a difference is found. Variants: "bid package", "bidding documents", "IFB" (issued for bid), "addendum", "conformed set".

  • "Bid set issued 03/02; pre-bid meeting 03/09; questions due 03/16; bids due 03/30."

  • "Addendum 2 revises the storefront hardware; bidders to acknowledge on the bid form."

3. How to read it in the minutes

  • If you read "per the bid set" on site → check the conformed set: an addendum or negotiation may have changed it.

  • If you read "addendum" → it changed the bid documents before award and is part of the contract.

  • If you read "clarification" by phone → it binds no one: only written addenda count.

  • If you read "conformed set to follow" → until it's issued, track which sheets changed.

4. Who does what

Party

What it means to them

What they do

Owner

It awards the contract

Approves the bid set, selects the bidder

Architect

It prepares and answers during bidding

Issues the set, answers questions by addendum, prepares the conformed set

Bidders

They price what they receive

Ask questions in writing, acknowledge addenda

Contractor

It builds the signed contract

Works from the conformed set, not the bid set

5. What it changes in practice

Minutes that track addenda and the conformed set keep the field on the right version. Failure scenario: a change agreed during negotiation never reaches the drawings. The bid-set version gets built, and the correction becomes a dispute over who pays.

6. Typical wording

"Bids due 03/30, 2:00 PM. Addenda 1 to 3 issued. Questions received after 03/16 will not be answered."

"Manhole MH-3 location: conformed set Rev. 3 governs (moved 6 ft per post-bid negotiation). Bid set superseded."

7. What to watch

  • Answer bidder questions only by written addendum.

  • List addenda in the minutes, with their dates.

  • Issue a conformed set promptly after award.

  • Mark the bid set superseded on site.

  • Check that drawings, specifications and bid form agree before issue.

  • Record the bid due date, time and place.

8. Don't confuse with

Related term

Key difference

Contract Documents

What was signed; governs after award

Conformed set

Contract Documents with addenda and accepted alternates incorporated

Permit set

Filed with the building department; may differ from the bid set

Addendum

Changes the bid documents before award

9. Related terms

Same phase: Design phases, Specifications, Bid form and schedule of values, Drawing revision. Same party: Owner, Architect.

Sources: AIA A701–2018 summary · AIA A701–2018 instructions

Template: Design meeting minutes

<-

BACK TO FULL GLOSSARY