Bid form and schedule of values: what the Architect needs to know so a quantity doesn't become a claim.
OAC meeting #16. The tile subcontractor submits a proposal for 430 sq ft "missed" in the schedule of values. The contract is a stipulated sum, and the drawings showed the area. A quantity missing from a breakdown is not, by itself, extra work.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Price breakdown | Procurement and construction | Owner, Architect, Contractor | Payments, change pricing | Keep the price tied to the documents | Pay applications, change log |
1. Definition and common mistake
The bid form is the document bidders fill in to state their price: base bid, alternates, unit prices, allowances. After award, A201–2017 §9.2 requires the Contractor to submit, before the first Application for Payment, a schedule of values allocating the entire Contract Sum to the various portions of the Work. The Architect reviews it and may object; it becomes the basis for progress payments (G702/G703).
Common mistake: paying a proposal because a line or a quantity was missing from the schedule of values. On a stipulated-sum contract, the price covers the Work shown and specified in the Contract Documents. Only work outside those documents can justify a change.
2. When it appears
The terms appear during bidding (alternates, unit prices, bid leveling), in the first pay application, and later whenever a change is priced against existing lines. Variants: "SOV", "G703", "continuation sheet", "bid tab", "deduct alternate".
"Alternate 2 (porcelain tile in lobby) accepted; SOV line 09 30 00 updated accordingly."
"Contractor's SOV front-loads general conditions; Architect to return with comments."
3. How to read it in the minutes
If you read "missed in the SOV" → check the drawings and specs first: if the work is shown, it is in the price.
If you read "unit price" → the price was set in the bid form; only the quantity is measured.
If you read "front-loaded" → early lines are inflated: object before the first payment.
If you read "allowance" → the final cost is adjusted against the allowance, up or down.
4. Who does what
Party | What it means to them | What they do |
|---|---|---|
Owner | It pays against the schedule | Approves payments certified by the Architect |
Architect | It reviews the breakdown and pay requests | Reviews the SOV, certifies payments, prices changes against it |
Contractor | It structures its billing | Prepares the SOV and bills monthly against it |
Subcontractors | Their packages roll up into the SOV | Provide breakdowns to the Contractor |
5. What it changes in practice
A schedule of values organized like the specifications makes payments and changes easy to check. Failure scenario: the minutes accept a "missed quantity" proposal. Two months later, three more trades ask for the same, citing the minutes as precedent.
6. Typical wording
"Tile proposal for 430 sq ft: area shown on A-601 and specified in 09 30 13. Included in Contract Sum; proposal rejected."
"SOV accepted with comments 05/02: general conditions spread over the duration of the Work."
7. What to watch
Compare any "missing quantity" with the drawings and specifications.
Ask for an SOV organized by specification section.
Object to front-loading before the first payment.
Price changes with the unit prices in the bid form when they exist.
Track allowances and alternates on their own lines.
Record in the minutes why a proposal is accepted or rejected.
8. Don't confuse with
Related term | Key difference |
|---|---|
Estimate | The design team's forecast; the bid is the Contractor's price |
Unit price contract | Paid by measured quantity, unlike a stipulated sum |
Change Order | Changes the Contract Sum; the SOV only allocates it |
Bid tab | Comparison of bids, not a contract document |
9. Related terms
Same phase: Bid documents, Specifications, Change Order, Application for Payment. Same party: Owner, Architect.
Sources: AIA Contract Documents: what is a schedule of values · AIA A701–2018 summary
Template: Design meeting minutes
<-