Change Order

Change Order: what the Architect needs to know so no line in the minutes is read as one.

The drywall subcontractor proposes a different partition type to save three weeks. At the OAC meeting, the Owner's Rep says it "sounds fine". The minutes record "approved in principle". The work starts. Two months later the price comes in at $84,000, and the Owner never signed anything. A Change Order is the only document that changes the Contract Sum or Time by agreement. The minutes track it; they never stand in for it.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Contract instrument

Construction

Owner, Architect, Contractor

High

Contractual, financial

General Notes, change log, action items

1. Definition and common mistake

A Change Order is a written instrument, signed by the Owner, the Contractor and the Architect, that records their agreement on three points. They are a change in the Work, the amount of any adjustment to the Contract Sum, and the extent of any adjustment to the Contract Time. The AIA form is G701.

A201-2017 §7.1 provides three ways to change the Work: Change Order (§7.2), Construction Change Directive (§7.3), and order for a minor change (§7.4, form G710). A Construction Change Directive (CCD) is signed by the Owner and the Architect without the Contractor, when price or time is not agreed. A minor change can't change price or time. On federal work, changes follow FAR 52.243-4 and are signed by the Contracting Officer. On public agency work, the agency's own General Conditions apply.

Common mistake: "approved in principle" in the minutes. Courts look at substance, and minutes that record agreement on work and price can be read as a change, or as a waiver of the written requirement.

2. When it appears

The term appears in the change log, the General Notes, pay applications and the monthly report. A change usually starts as an RFI, an ASI or a field condition. It then becomes a PCO (potential change order) or a COR (change order request), and ends as a Change Order. Variants include "CO", "change order proposal" and "bulletin". Typical wording:

  • "PCO 23 priced at $12,400, under Owner review."

  • "CO 7 executed, adds 5 days to the Contract Time."

3. How to read it in the minutes

  • If you read "approved in principle" or "proceed" → no Change Order exists yet: ask for a CCD or a signed CO.

  • If you read a price with no CO number → it's a proposal, not an agreement.

  • If you read "no cost" with no time → ask whether time is also waived.

  • If you read work proceeding on a pending PCO → record who directed it and on what instrument.

4. Who does what

Party

What a Change Order means to them

What they do

Owner

It commits money and time

Signs, or issues a CCD

Architect

It prepares and certifies the change

Prepares the CO, signs, tracks the log

Contractor

It gets paid and gets time for changed work

Prices, signs, proceeds

Subcontractors

They work through the Contractor

Price to the Contractor, never directly to the Owner

5. What it changes in practice

When the minutes track each change by number, amount and status, and say plainly that listing a change is not a Change Order, disputes stay small. When the minutes record "agreed" and "proceed", the Owner may owe for work it never priced.

Failure scenario: three items marked "approved in principle" are built without a CO. At closeout the Contractor bills $210,000 and cites the minutes. The Owner argues the written CO requirement. The Contractor argues waiver, pointing to the Owner's Rep's presence at each meeting. Settlement costs more than the original prices would have.

6. Typical wording

"PCO 23, partition type change: priced $12,400, 0 days. Ball in court: Owner. Listing this proposal is not a Change Order."

"CO 7 executed 10/14: +$31,200, +5 days."

7. What to watch

  • Write in the General Notes that listing a proposal is not a Change Order.

  • Number every PCO and carry it until it is executed or withdrawn.

  • Use a CCD when work must proceed before price is agreed.

  • Record time and price together, even when one of them is zero.

  • Check who can sign for the Owner before the first change.

8. Don't confuse with

Related term

Key difference

Construction Change Directive

Signed without the Contractor; price settled later

ASI / minor change

No change in price or time

PCO / COR

A proposal or request, not an agreement

Field order

An instruction on site; needs a CO if cost or time changes

9. Related terms

Same phase (construction): Construction Change Directive, ASI, RFI, Schedule of Values. Same party (Owner): Liquidated damages, Application for Payment, Retainage, Substantial Completion.

<-