Change Order: what the Architect needs to know so no line in the minutes is read as one.
The drywall subcontractor proposes a different partition type to save three weeks. At the OAC meeting, the Owner's Rep says it "sounds fine". The minutes record "approved in principle". The work starts. Two months later the price comes in at $84,000, and the Owner never signed anything. A Change Order is the only document that changes the Contract Sum or Time by agreement. The minutes track it; they never stand in for it.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Contract instrument | Construction | Owner, Architect, Contractor | High | Contractual, financial | General Notes, change log, action items |
1. Definition and common mistake
A Change Order is a written instrument, signed by the Owner, the Contractor and the Architect, that records their agreement on three points. They are a change in the Work, the amount of any adjustment to the Contract Sum, and the extent of any adjustment to the Contract Time. The AIA form is G701.
A201-2017 §7.1 provides three ways to change the Work: Change Order (§7.2), Construction Change Directive (§7.3), and order for a minor change (§7.4, form G710). A Construction Change Directive (CCD) is signed by the Owner and the Architect without the Contractor, when price or time is not agreed. A minor change can't change price or time. On federal work, changes follow FAR 52.243-4 and are signed by the Contracting Officer. On public agency work, the agency's own General Conditions apply.
Common mistake: "approved in principle" in the minutes. Courts look at substance, and minutes that record agreement on work and price can be read as a change, or as a waiver of the written requirement.
2. When it appears
The term appears in the change log, the General Notes, pay applications and the monthly report. A change usually starts as an RFI, an ASI or a field condition. It then becomes a PCO (potential change order) or a COR (change order request), and ends as a Change Order. Variants include "CO", "change order proposal" and "bulletin". Typical wording:
"PCO 23 priced at $12,400, under Owner review."
"CO 7 executed, adds 5 days to the Contract Time."
3. How to read it in the minutes
If you read "approved in principle" or "proceed" → no Change Order exists yet: ask for a CCD or a signed CO.
If you read a price with no CO number → it's a proposal, not an agreement.
If you read "no cost" with no time → ask whether time is also waived.
If you read work proceeding on a pending PCO → record who directed it and on what instrument.
4. Who does what
Party | What a Change Order means to them | What they do |
|---|---|---|
Owner | It commits money and time | Signs, or issues a CCD |
Architect | It prepares and certifies the change | Prepares the CO, signs, tracks the log |
Contractor | It gets paid and gets time for changed work | Prices, signs, proceeds |
Subcontractors | They work through the Contractor | Price to the Contractor, never directly to the Owner |
5. What it changes in practice
When the minutes track each change by number, amount and status, and say plainly that listing a change is not a Change Order, disputes stay small. When the minutes record "agreed" and "proceed", the Owner may owe for work it never priced.
Failure scenario: three items marked "approved in principle" are built without a CO. At closeout the Contractor bills $210,000 and cites the minutes. The Owner argues the written CO requirement. The Contractor argues waiver, pointing to the Owner's Rep's presence at each meeting. Settlement costs more than the original prices would have.
6. Typical wording
"PCO 23, partition type change: priced $12,400, 0 days. Ball in court: Owner. Listing this proposal is not a Change Order."
"CO 7 executed 10/14: +$31,200, +5 days."
7. What to watch
Write in the General Notes that listing a proposal is not a Change Order.
Number every PCO and carry it until it is executed or withdrawn.
Use a CCD when work must proceed before price is agreed.
Record time and price together, even when one of them is zero.
Check who can sign for the Owner before the first change.
8. Don't confuse with
Related term | Key difference |
|---|---|
Construction Change Directive | Signed without the Contractor; price settled later |
ASI / minor change | No change in price or time |
PCO / COR | A proposal or request, not an agreement |
Field order | An instruction on site; needs a CO if cost or time changes |
9. Related terms
Same phase (construction): Construction Change Directive, ASI, RFI, Schedule of Values. Same party (Owner): Liquidated damages, Application for Payment, Retainage, Substantial Completion.
<-