Change Order Request

Change Order Request: what the Architect needs to know so no change is built before it is priced and signed.

Nine change requests are open in the log. Three are past their pricing date, and the drywall subcontractor has already ordered material for one of them. A Change Order Request (PCO or COR) is a proposal, not an agreement: until a Change Order or a Construction Change Directive is signed, the change isn't part of the Contract and can't be paid or rejected cleanly.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Tracking document

Construction

Architect, Owner, Contractor, cost consultant

High

Contractual, financial

Change log, action items, General Notes

1. Definition and common mistake

A Change Order Request is the Contractor's priced proposal for a change in the Work. It describes the change (added, deleted or revised work), its origin (Owner request, concealed condition, design error, RFI response) and its effect on the Contract Sum and the Contract Time. Many logs call it a PCO (potential change order) or a COR (change order request). When the Architect asks for the price first, the request is usually issued on AIA G709, Proposal Request.

The request is a working document; AIA A201-2017 doesn't define it. What changes the Contract is the instrument that closes it: a Change Order signed by the Owner, the Contractor and the Architect (§7.2), or a Construction Change Directive signed by the Owner and the Architect when price or time isn't agreed (§7.3). A claim for added cost or time follows its own notice rules, generally within 21 days of the event (§15.1.2–15.1.3). On federal work, changes follow FAR 52.243-4.

Common mistake: treating a submitted price, or a nod in the meeting, as permission to proceed. Without a CO or a CCD, the Contractor works at its own risk and the Owner may refuse to pay.

2. When it appears

In the change log carried in the minutes, usually one line per request: number, description, origin, date issued, price, days requested, status and ball in court. It appears in every kind of project, with a general contractor or a CM at-risk, and grows fastest during fit-out and after design changes. Variants: PCO, COR, CCR, change order proposal, change event.

Typical wording: “PCO 14, revised partition type at Level 4: priced $12,400, 0 days. Ball in court: Owner.” “COR 9: Contractor to resubmit with backup by Friday.”

3. How to read it in the minutes

If you read “under review” → check who holds it and since when; add a due date for the decision.

If you read “priced, awaiting response” → the Owner owes a decision: carry it as an action item with its ball in court.

If you read “approved in principle” or “proceed” → no instrument exists yet: ask for a CO, or a CCD if the work can't wait.

If you read “ordered” or “in progress” on an open request → record who directed it and on what document.

4. Who does what

Party

What the request means to them

What they do

Architect

A change to describe, review and certify

Issue the proposal request, review the price, prepare the CO or CCD

Contractor

A price and a time impact to justify

Submit pricing with backup within the requested time, state the days

Owner

A financial decision

Accept, reject or direct by CCD; sign the CO

Cost consultant

A price to check

Compare with unit prices, allowances and the schedule of values

5. What it changes in practice

A change log kept current lets the Architect tell the Owner, at any meeting, how much is committed, how much is pending and how many days are at stake. Without it, changes pile up in conversation and come back at closeout as claims nobody priced.

Failure scenario: a flooring change is agreed verbally in the OAC meeting. The Contractor orders the material and bills it on the next pay application. The Owner disputes it, and the Contractor points to the minutes. With no CO, no CCD and no agreed price, the dispute runs to closeout, and costs more than the change itself.

6. Typical wording

“PCO 14, revised partition type at Level 4: priced 10/02, $12,400, 0 days. Ball in court: Owner. Listing this request is not a Change Order.”

“COR 9, concealed duct conflict at Level 2: price requested by 10/16. Ball in court: Contractor.”

7. What to watch

  • Number every request, including the ones withdrawn or rejected.

  • Ask for the time impact with the price; days that aren't requested in time are hard to recover.

  • Track deductive changes as closely as additive ones.

  • Use a Construction Change Directive when work must proceed before price is agreed.

  • Write in the General Notes that listing a request is not a Change Order.

8. Don't confuse with

Related term

Key difference

Change Order

The signed instrument that changes the Contract Sum or Time

Construction Change Directive

Directs the change before price is agreed; signed without the Contractor

ASI / minor change

Clarification or minor change with no cost or time

Claim

A demand for cost or time under A201 Article 15, with its own notice rules

9. Related terms

Same phase (changes): Change Order · Construction Change Directive · ASI · RFI

Same party (Architect / Contractor): Schedule of Values · Application for Payment · Ball in court · OAC meeting

<-