Changes in the Work

Changes in the Work: what the Architect needs to know so extra work is authorized before it is built.

During the walkthrough, the Owner asks for an extra door in the corridor. The Contractor says “no problem” and builds it. Two months later the invoice arrives, the Owner says it was included, and the minutes only say “door added, OK”. Under A201, a change has its own instruments. The minutes record the request; they don't authorize it.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Contract procedure

Construction

Owner, Architect, Contractor

High

Cost, schedule, contract

Change log, RFI and PCO log

1. Definition and common mistake

Changes in the Work are additions, deletions or modifications to the Work after the Contract is signed. A201-2017 Article 7 gives three instruments: a Change Order signed by the Owner, Contractor and Architect, agreeing on scope, price and time (§7.2); a Construction Change Directive signed by the Owner and Architect, directing a change when price or time aren't yet agreed (§7.3); and an order for a minor change by the Architect, with no change in price or time and consistent with the intent of the Contract Documents (§7.4).

Before any of these, the Contractor usually prices the request through a proposal request or a Potential Change Order (PCO).

Common mistake: treating “OK” in the minutes as authorization. The minutes record what was said; they don't replace a signed instrument.

2. When it appears

In the change log and in each topic where a request starts: Owner request, design clarification, differing conditions, code requirement. Lines often follow the sequence: request, proposal, review, Change Order or CCD. Variants: change request, extra work, added work, scope change.

Typical wording: “Owner request: added door corridor L2. Proposal request issued 04/03. Ball in court: Contractor.” “PCO 12 accepted by the Owner; Change Order 5 to be issued.”

3. How to read it in the minutes

If you read “OK” or “accepted” on a change → check that a Change Order or CCD follows.

If work starts before pricing → a CCD protects both sides; record it.

If the change affects time → it must be stated in the instrument, not later.

If the Architect calls something a minor change → check it has no cost or time impact.

4. Who does what

Party

What a change means to them

What they do

Owner

A decision on scope and cost

Request, approve, sign

Architect

Contract administration

Issue proposal requests, prepare Change Orders and CCDs

Contractor

Work to price and schedule

Submit PCO, proceed after authorization

Subcontractors

Through the Contractor

Price and perform

5. What it changes in practice

A change log tied to signed instruments lets everyone know the contract sum at any time. Changes agreed only verbally pile up into a dispute at final payment.

Failure scenario: fifteen changes recorded as “OK” in the minutes, none formalized. At closeout, the Contractor claims $180,000; the Owner recognizes $60,000. Months of negotiation follow.

6. Typical wording

“Added door corridor L2: PCO 14, $3,200, no time impact. Owner approved 04/12. Change Order 6 to be issued. Ball in court: Architect.”

“Fire damper relocation: CCD 2 issued 05/03, pricing pending. Ball in court: Contractor.”

7. What to watch

  • Number each change and keep it until signed.

  • Separate proposal, approval and instrument.

  • State price and time in the same instrument.

  • Use a CCD when work can't wait for pricing.

  • Never let the minutes stand for a Change Order.

8. Don't confuse with

Related term

Key difference

Change Order

The signed instrument that changes the Contract

Change Order Request (PCO)

The Contractor's priced proposal

Construction Change Directive

Directs the change before agreement

RFI

A question, not a change

9. Related terms

Same phase (construction): Change Order · Change Order Request (PCO) · Ball in court · Contractor default