Construction Change Directive: what the Architect needs to know when work must proceed before price is agreed.
OAC meeting #19. The fire marshal requires an extra exit sign circuit before inspection next week. The Contractor's price is twice the Architect's estimate. Waiting for agreement would delay occupancy. A Construction Change Directive lets the work proceed now and settles the price later.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Contract instrument | Construction | Owner, Architect, Contractor | Cost, time | Proceed without losing control of price | Change log, action items |
1. Definition and common mistake
A Construction Change Directive (CCD) is a written order prepared by the Architect and signed by the Owner and the Architect, directing a change in the Work before the Owner and Contractor agree on its effect on the Contract Sum or Time (A201–2017 §7.3; AIA form G714). The Contractor must proceed promptly. The CCD states a proposed method of adjustment: lump sum, unit prices, or cost plus fee. Once price and time are agreed, a Change Order supersedes it.
Common mistake: treating a CCD as the final price. It authorizes the work; the adjustment is settled later, by agreement or under §7.3, and the Contractor may disagree and make a Claim.
2. When it appears
CCDs appear in the change log and OAC minutes when a change is urgent or price talks stall. Variants: "CCD", "G714", "directive", "proceed under CCD", "T&M".
"CCD 03 issued 10/02: additional exit sign circuit, cost plus fee, not-to-exceed $9,500."
"Contractor disputes the CCD 02 time adjustment; Claim notice received."
3. How to read it in the minutes
If you read "proceed" with no CO or CCD → ask for a CCD before work starts.
If you read "CCD" → work goes ahead; price and time are still open.
If you read "T&M" → make sure daily records are signed and kept.
If you read "CCD signed by Contractor" → that signature means agreement: a Change Order should follow.
4. Who does what
Party | What it means to them | What they do |
|---|---|---|
Owner | It authorizes work before price | Signs the CCD with the Architect |
Architect | It prepares and administers | Drafts the CCD, sets the method, determines the adjustment if needed |
Contractor | It must proceed | Proceeds promptly, keeps cost records, states agreement or disagreement |
Subcontractors | They perform the change | Track labor and materials daily |
5. What it changes in practice
A CCD keeps urgent work moving without a blank check. Minutes that track each CCD's status (method, cap, records, conversion to a Change Order) keep it from becoming a dispute. Failure scenario: work proceeds on "go ahead" with no CCD; the cost records are thin, and the final price turns into a negotiation with no basis.
6. Typical wording
"CCD 03: exit sign circuit, cost plus 10% fee, NTE $9,500. Daily T&M sheets to the Architect each Friday. Convert to CO when agreed."
"CCD 01 superseded by CO 6 (+$7,820, +2 days)."
7. What to watch
Issue a CCD whenever work must start before price is agreed.
State the method of adjustment and any cap.
Require daily cost records for cost-plus CCDs.
Track every open CCD until a Change Order supersedes it.
Note the Contractor's agreement or disagreement in the minutes.
Don't let "proceed" in the minutes stand in for a signed CCD.
8. Don't confuse with
Related term | Key difference |
|---|---|
Change Order | Signed by all three; price and time agreed |
Minor change (ASI, G710) | No change in price or time |
Field order | Site instruction; needs a CCD or CO if cost or time changes |
Claim | The Contractor's demand when it disagrees |
9. Related terms
Same phase (construction): Change Order, Changes in the Work, Change Order Request, Stop-work order. Same party: Owner, Architect.
Sources: AIA G714–2017 instructions · AIA G714–2017 summary
<-