Construction Change Directive

Construction Change Directive: what the Architect needs to know when work must proceed before price is agreed.

OAC meeting #19. The fire marshal requires an extra exit sign circuit before inspection next week. The Contractor's price is twice the Architect's estimate. Waiting for agreement would delay occupancy. A Construction Change Directive lets the work proceed now and settles the price later.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Contract instrument

Construction

Owner, Architect, Contractor

Cost, time

Proceed without losing control of price

Change log, action items

1. Definition and common mistake

A Construction Change Directive (CCD) is a written order prepared by the Architect and signed by the Owner and the Architect, directing a change in the Work before the Owner and Contractor agree on its effect on the Contract Sum or Time (A201–2017 §7.3; AIA form G714). The Contractor must proceed promptly. The CCD states a proposed method of adjustment: lump sum, unit prices, or cost plus fee. Once price and time are agreed, a Change Order supersedes it.

Common mistake: treating a CCD as the final price. It authorizes the work; the adjustment is settled later, by agreement or under §7.3, and the Contractor may disagree and make a Claim.

2. When it appears

CCDs appear in the change log and OAC minutes when a change is urgent or price talks stall. Variants: "CCD", "G714", "directive", "proceed under CCD", "T&M".

  • "CCD 03 issued 10/02: additional exit sign circuit, cost plus fee, not-to-exceed $9,500."

  • "Contractor disputes the CCD 02 time adjustment; Claim notice received."

3. How to read it in the minutes

  • If you read "proceed" with no CO or CCD → ask for a CCD before work starts.

  • If you read "CCD" → work goes ahead; price and time are still open.

  • If you read "T&M" → make sure daily records are signed and kept.

  • If you read "CCD signed by Contractor" → that signature means agreement: a Change Order should follow.

4. Who does what

Party

What it means to them

What they do

Owner

It authorizes work before price

Signs the CCD with the Architect

Architect

It prepares and administers

Drafts the CCD, sets the method, determines the adjustment if needed

Contractor

It must proceed

Proceeds promptly, keeps cost records, states agreement or disagreement

Subcontractors

They perform the change

Track labor and materials daily

5. What it changes in practice

A CCD keeps urgent work moving without a blank check. Minutes that track each CCD's status (method, cap, records, conversion to a Change Order) keep it from becoming a dispute. Failure scenario: work proceeds on "go ahead" with no CCD; the cost records are thin, and the final price turns into a negotiation with no basis.

6. Typical wording

"CCD 03: exit sign circuit, cost plus 10% fee, NTE $9,500. Daily T&M sheets to the Architect each Friday. Convert to CO when agreed."

"CCD 01 superseded by CO 6 (+$7,820, +2 days)."

7. What to watch

  • Issue a CCD whenever work must start before price is agreed.

  • State the method of adjustment and any cap.

  • Require daily cost records for cost-plus CCDs.

  • Track every open CCD until a Change Order supersedes it.

  • Note the Contractor's agreement or disagreement in the minutes.

  • Don't let "proceed" in the minutes stand in for a signed CCD.

8. Don't confuse with

Related term

Key difference

Change Order

Signed by all three; price and time agreed

Minor change (ASI, G710)

No change in price or time

Field order

Site instruction; needs a CCD or CO if cost or time changes

Claim

The Contractor's demand when it disagrees

9. Related terms

Same phase (construction): Change Order, Changes in the Work, Change Order Request, Stop-work order. Same party: Owner, Architect.

Sources: AIA G714–2017 instructions · AIA G714–2017 summary

<-