Construction scheduling: what the Architect needs to know so delays are measured against a schedule, not felt.
The Contractor says the job is on time. The drywall is two weeks behind, the elevator one week, and the update hasn't been submitted for two months. Without a current schedule, nobody can say whether the end date has moved. Scheduling is how the project knows where it stands.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Management function | Construction | Contractor, Architect, Owner, scheduler | High | Schedule | Schedule section, lookahead |
1. Definition and common mistake
Construction scheduling plans and tracks the sequence of activities to finish on time. Most US projects use the critical path method (CPM): activities linked by logic, with the critical path being the longest chain that sets the end date. The Contractor owns the schedule.
A201-2017 §3.10 requires the Contractor to submit a schedule and revise it as the Contract requires. Section 01 32 16 often sets update frequency, format and float rules. Time extensions are claimed through the Contract's procedures (§15.1.6), usually with a schedule analysis.
Common mistake: discussing delays without a current update. A delay off the critical path may not move the end date at all.
2. When it appears
In the schedule section of every OAC meeting: monthly updates, three-week lookaheads, critical activities, delays and recovery. Variants: CPM schedule, master schedule, lookahead, time impact analysis.
Typical wording: “Schedule update April received 05/03: Substantial Completion unchanged, 4 days of float left on elevator path.” “Drywall L5 two weeks behind; recovery plan requested.”
3. How to read it in the minutes
If no update is mentioned for over a month → ask for it.
If a delay is announced → ask whether it is on the critical path.
If float disappears → ask who owns it under the Contract.
If a time extension is requested → it goes through the Contract's claim process, not the minutes.
4. Who does what
Party | What scheduling means to them | What they do |
|---|---|---|
Contractor | Its plan | Build, update, recover |
Architect | Contract administration | Review, record, advise on time claims |
Owner | Its dates | Decide on extensions and acceleration |
Subcontractors | Their activities | Report progress through the Contractor |
5. What it changes in practice
A current schedule turns delay discussions into facts. A stale one turns them into opinions, and claims become hard to settle.
Failure scenario: no update for three months. At the end, the Contractor claims 40 days; the Owner applies liquidated damages. Neither can show the critical path at the time.
6. Typical wording
“April update received 05/03. Critical path: elevator install, float 4 days. Info.”
“Drywall L5: 10 days behind, not critical. Recovery plan due 05/10. Ball in court: Contractor.”
7. What to watch
Require updates at the frequency the specifications set.
Track the critical path and float, not only dates.
Ask for recovery plans when activities slip.
Leave time claims to the Contract's process.
Keep each update with its date.
8. Don't confuse with
Related term | Key difference |
|---|---|
Baseline schedule | The first accepted schedule |
Lookahead | Short-term detail |
Time impact analysis | Measures one delay's effect |
Liquidated damages | Compensation for late completion |
9. Related terms
Same phase (construction): Baseline schedule and look-ahead · Schedule acceptance · Weather delay day · Liquidated damages
Same party (Contractor / Architect): OAC meeting · Ball in court · Stop-work order · Contractor default
<-