Consulting engineers: what the Architect needs to know about which engineer the minutes mean.
Design meeting #10. "Waiting on the engineer." There are three on the project: the structural and MEP engineers on the design team, and the truss manufacturer's delegated engineer. Three weeks go by with no one following up with the right one.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Design team member | Design and construction | Architect, structural, MEP, civil engineers, delegated engineers | Coordination, liability | Name the right engineer | Attendance, action items, submittals |
1. Definition and common mistake
Consulting engineers design the building's systems: structural, mechanical, electrical, plumbing and fire protection (MEP/FP), civil. On most building projects they are hired by the Architect as consultants, sometimes directly by the Owner. Their drawings and calculations are sealed by a licensed professional engineer (PE or SE), as state law and the building code require. A delegated design engineer, hired by a contractor or supplier, designs a component (trusses, curtain wall, fire sprinklers) to criteria set by the design team.
Common mistake: writing "the engineer" without saying which one. The design team's engineer and a delegated engineer have different roles and different responsibilities.
2. When it appears
Engineers appear in attendance lists, action items, RFI responses and submittal reviews. Variants: "SE", "EOR" (engineer of record), "MEP", "MEP/FP", "civil", "delegated design", "specialty engineer".
"Structural EOR to confirm the opening in the slab at grid D/4 by 09/18."
"Delegated design submittal for trusses, sealed by the manufacturer's engineer, to be reviewed by the structural EOR."
3. How to read it in the minutes
If you read "the engineer" → name the firm and the discipline.
If you read "EOR" → it's the engineer of record for that discipline on the design team.
If you read "delegated design" → the component's designer is another engineer, reviewed by the EOR.
If you read "engineer to confirm" → put a date and a follow-up owner on it.
4. Who does what
Party | What it means to them | What they do |
|---|---|---|
Architect | It coordinates the consultants | Assigns questions, tracks answers, integrates the systems |
Engineer of record | It is responsible for its discipline | Designs, seals, answers RFIs, reviews related submittals |
Delegated engineer | It designs one component | Seals its design to the stated criteria |
Contractor | It builds the engineered systems | Submits shop drawings and delegated designs for review |
5. What it changes in practice
Minutes that name the engineer, the discipline and the date get answers. Failure scenario: an MEP question noted as "engineer to review" sits for weeks; the ceiling is framed before the duct size is confirmed, and part of it comes down.
6. Typical wording
"MEP engineer (mechanical) to confirm duct size above corridor 2B by 10/04; ceiling framing on hold in that area."
"Structural EOR reviewed the delegated steel stair design: no exceptions taken."
7. What to watch
Name the firm and the discipline every time.
Separate the engineer of record from delegated engineers.
Put each technical question on the action list with a date.
Check that sealed documents match the current revision.
Invite the right engineer when a topic is on the agenda.
Note who owns coordination between disciplines.
8. Don't confuse with
Related term | Key difference |
|---|---|
Architect | Leads and coordinates the design team |
Delegated design engineer | Works for a contractor or supplier, on one component |
Special inspector | Verifies construction for the Owner and building official |
Code consultant | Advises on code compliance; doesn't design systems |
9. Related terms
Same party: Architect, Owner, Special inspection. Same phase: Engineering calculations, MEP coordination, Submittal review.