Contractor default: what the Architect needs to know so the record is ready if the Owner has to act.
The drywall subcontractor stopped showing up three weeks ago. The minutes say “understaffed” each meeting, then “absent”. The Owner asks whether it can bring in another firm. The answer depends on notices the Contract requires, not on how many times the minutes said “absent”.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Contract situation | Construction | Owner, Architect, Contractor, surety | High | Schedule, cost, contract | Staffing and schedule section, follow-up items |
1. Definition and common mistake
Contractor default is the Contractor's failure to perform under the Contract: not supplying enough workers or materials, not paying subcontractors, disregarding laws or the Architect's instructions, or otherwise materially breaching the Contract.
A201-2017 gives the Owner two main paths. Under §2.5, if the Contractor defaults or neglects to carry out the Work and fails within ten days after written notice to begin and continue correction, the Owner may correct the deficiencies and deduct the cost. Under §14.2, for listed reasons, the Owner may terminate for cause after the Initial Decision Maker certifies sufficient cause and after seven days' written notice. If there is a performance bond, the surety has its own notice steps.
Common mistake: calling a subcontractor “in default” in the minutes. The Owner's contract is with the Contractor; default is the Contractor's, even when a subcontractor is the cause.
2. When it appears
In staffing and schedule items, then in follow-up items when the situation lasts: workforce below plan, missed dates, unpaid subcontractors, repeated nonconforming work. It becomes a topic of its own when the Owner considers notice.
Typical wording: “Drywall: 2 workers on site vs 8 planned. Contractor to submit recovery plan by 06/14.” “Owner's notice under §2.5 sent 06/18.”
3. How to read it in the minutes
If you read the same staffing gap at three meetings → ask the Contractor for a recovery plan in writing.
If the Owner considers action → the notice goes by the method the Contract requires, not through the minutes.
If a bond exists → the surety must be notified as the bond requires.
If the minutes name a subcontractor as defaulting → rewrite: the Contractor answers for its subcontractors.
4. Who does what
Party | What default means to them | What they do |
|---|---|---|
Owner | A right to act | Send notices, decide on correction or termination |
Architect | Facts and certification steps | Record facts, advise, certify costs if asked |
Contractor | Its obligation | Cure, explain, submit recovery plan |
Surety | Its bond obligation | Respond to notice |
5. What it changes in practice
Precise minutes (dates, workforce counts, ball in court) give the Owner a reliable chronology if it must act. Vague minutes make every notice harder to defend.
Failure scenario: the Owner brings in another drywall firm without a §2.5 notice. The Contractor disputes the back-charge; the minutes say “understaffed” but no notice was ever sent.
6. Typical wording
“Drywall L3–L4: 2 workers vs 8 planned for 3 weeks. Recovery plan due 06/14. Ball in court: Contractor.”
“Owner notice under A201 §2.5 sent 06/18 (by certified mail). Info.”
7. What to watch
Record facts: dates, counts, missed milestones.
Address the Contractor, never the subcontractor, in contract terms.
Leave notices to the Owner, by the Contract's method.
Notify the surety when a bond exists.
Keep the follow-up numbering unbroken.
8. Don't confuse with
Related term | Key difference |
|---|---|
Follow-up item | A repeated request, not a notice |
Stop-work order | The Owner stops the Work, not a default |
Liquidated damages | Delay compensation set in the Agreement |
Termination for convenience | Owner's choice, without default (§14.4) |
9. Related terms