Floor release: what the Architect needs to know so a level isn't handed on with work missing and nobody noticing.
The structure trade leaves Level 6. The MEP trades move in and find missing sleeves, a shoring post still in place and debris in the shafts. Each trade says the floor was released that way. A dated floor release, with a short list, decides who fixes what.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Coordination step | Structure, finishes | Contractor, outgoing and incoming trades, Architect | Medium | Quality, schedule, back-charges | Schedule section, trade coordination |
1. Definition and common mistake
A floor release is a dated check, usually a walk, that a level is ready to pass from one phase or trade to the next: structure to MEP rough-in, rough-in to drywall, drywall to finishes. It records the condition of the floor, open items and who must close them.
It's a coordination practice under the Contractor's responsibility for sequencing (A201-2017 §3.3). It works like an area turnover but follows the vertical progress of the building, level by level.
Common mistake: moving trades by schedule date only, without a walk. Problems found later are hard to attribute.
2. When it appears
In the schedule section and trade coordination, at each level as the building rises and as finishes progress. Variants: floor turnover, level release, “floor ready for”.
Typical wording: “Level 6 released by structure to MEP 05/15. Open items: 3 sleeves, shoring removal, shaft cleaning.” “Level 4 released to drywall after in-wall inspection.”
3. How to read it in the minutes
If a trade moves to a level with no release → ask for the walk.
If items stay open after release → track them with ball in court.
If a hold point applies → the release waits for it.
If damage appears later → the release date frames responsibility.
4. Who does what
Party | What the release means to them | What they do |
|---|---|---|
Contractor | Sequence | Organize the walk, record items |
Outgoing trade | Its work done | Close its items |
Incoming trade | Its start condition | Accept or report |
Architect | Record | Note dates and items |
5. What it changes in practice
Dated releases keep the vertical sequence moving and settle damage questions quickly.
Failure scenario: Level 6 drywall starts without release. Sleeves are missing; core drilling through finished walls costs a week and a dispute over who pays.
6. Typical wording
“Level 6 release structure → MEP 05/15: 3 open items (attached). Ball in court: Concrete subcontractor through the Contractor.”
“Level 4 released to drywall 06/02 after inspection HP-07. Info.”
7. What to watch
Walk each level before the next trade starts.
List open items with owners.
Link releases to hold points.
Date and photograph the condition.
Close items before final finishes.
8. Don't confuse with
Related term | Key difference |
|---|---|
Area turnover | Any area, any handoff |
Hold point | An inspection, not a handoff |
Substantial Completion | Contract milestone |
Punch list | End-of-job defects |
9. Related terms
Same phase (construction): Area turnover · Hold point · Grade beams · Benchmark
Same party (Contractor): Construction scheduling · Baseline schedule and look-ahead · OAC meeting · Ball in court
<-