Follow-up item

Follow-up item: what the Architect needs to know so a repeated request is useful on the day someone has to act.

“Follow-up 7” next to the plumbing closeout documents. Seven meetings, seven reminders, no answer, and still no letter. The counter shows the request was made and repeated; it triggers nothing on its own. The Architect and the Owner decide when a reminder has to become a written notice.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Tracking status

Construction, closeout

Architect, Contractor, Owner

High

Schedule, traceability

Action item log, status column

1. Definition and common mistake

A follow-up item is an action item that wasn't completed by its due date and is carried forward, with a counter showing how many meetings it has been open. The counter goes up at each meeting: Follow-up 1, Follow-up 2, and so on.

It's an industry usage term. The minutes record the repeated request, with its dates and its ball in court, and that record matters later. But a notice to cure is a separate act: under A201-2017, the Owner may correct the Contractor's default after a ten-day written notice (§2.5), and termination for cause has its own notice steps (§14.2). Liquidated damages apply only as the Agreement provides.

Common mistake: treating “Follow-up 7” as a notice or as grounds for withholding. It prepares the next step; it doesn't replace it.

2. When it appears

In the action item log, next to documents still due (closeout submittals, shop drawings, test reports) and actions not done. Firms write it as “Carried over x3”, “3rd request” or “Overdue x6”; the logic is the same. Some minutes turn the line red past a threshold.

Typical wording: “Plumbing O&M manuals: Follow-up 4.” “Window product data: Follow-up 2, due 03/21.”

3. How to read it in the minutes

If you read a follow-up past three → escalation is due: a call to the project manager, then a letter.

If the counter restarts at 1 with no reason → continuity is lost; correct it and keep the number.

If the item concerns safety → it goes beyond the minutes: notify the Contractor and the Owner in writing.

If you are the Contractor → answer in writing and ask that the answer be recorded in the next minutes.

4. Who does what

Party

What the follow-up means to them

What they do

Architect

A request not met

Keep the counter, recommend escalation, draft the notice if asked

Contractor

A recorded, dated delay

Act or explain in writing

Owner

A possible decision

Approve a notice or apply the Contract

Subcontractors

Through the Contractor

Respond through the Contractor

5. What it changes in practice

A counter kept without gaps dates the first request and shows the Architect's persistence. A counter that disappears or restarts can't show how long the item has been open.

Failure scenario: the HVAC closeout documents stay on follow-up for ten meetings. No letter goes out. At final payment, the Owner withholds; the Contractor disputes it, citing no notice. The minutes record the reminders, but the Contract's notice step was never taken.

6. Typical wording

“Plumbing O&M manuals: Follow-up 5. Notice sent by the Owner 05/02, response due in 10 days.”

“Sleeve layout, Level 2: Follow-up 2. Ball in court: Mechanical subcontractor through the Contractor.”

7. What to watch

  • Keep the same number from one meeting to the next.

  • Set an escalation threshold in the General Notes, for example at the third follow-up.

  • Send notices by the method the Contract requires, never through the minutes.

  • Cite the Agreement before mentioning liquidated damages.

  • Record the closing date when the item is finally done.

8. Don't confuse with

Related term

Key difference

Action item

First request, with its due date

Notice to cure

Written notice under the Contract

Liquidated damages

Set in the Agreement, separate from follow-ups

Closed item

Done and removed from active tracking

9. Related terms

Same phase (construction): Action item · Info item · Liquidated damages · Closed items

Same party (Architect / Contractor): Ball in court · Closeout submittals · Contractor default · OAC meeting

<-