MEP coordination

MEP coordination: what the Architect needs to know so a conflict is solved on paper, not on site.

OAC meeting #11. The concrete contractor places the level 1 deck. Three weeks later, the smoke exhaust duct doesn't fit: the opening was on the mechanical drawings, not on the formwork drawings. Skipped coordination is paid for with a core drill.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Coordination process

DD to construction

Architect, consultants, Contractor, MEP subcontractors

Rework, delay

Solve conflicts before installation

Coordination log, action items

1. Definition and common mistake

MEP coordination checks that structure, ductwork, piping, conduit, sprinklers and ceilings fit together in the same space. During design, the Architect coordinates its consultants' systems. During construction, Division 01 (often Section 01 31 00) typically requires the Contractor to prepare coordination drawings or a coordinated BIM model, led by a coordinator and resolved in coordination meetings with clash detection.

Common mistake: thinking that reviewing each trade's shop drawings amounts to coordination. A drawing can conform to the design and still clash with the trade next to it.

2. When it appears

Coordination appears in OAC minutes, coordination meeting minutes, RFIs and the clash log. Variants: "coordination drawings", "clash detection", "BIM coordination", "sign-off", "sleeves and openings".

  • "Level 2 corridor coordination: sprinkler main lowered 4 in. to clear the duct; sign-off by all trades 05/20."

  • "Sleeve drawings for level 3 deck due before rebar inspection on 06/02."

3. How to read it in the minutes

  • If you read "coordinated" → ask who signed off, and on which drawing.

  • If you read a clash with no owner → assign it with a date.

  • If you read "field route" → coordination was skipped: check the impact on ceilings and access.

  • If you read "openings per MEP" → confirm they appear on the structural or formwork drawings.

4. Who does what

Party

What it means to them

What they do

Architect

It sets ceiling heights and design intent

Answers coordination RFIs, protects clearances and access

Consulting engineers

Their systems must fit

Resolve conflicts within design intent

Contractor / coordinator

It runs the process

Leads coordination meetings, keeps the clash log, collects sign-offs

MEP subcontractors

They model and install

Model their work, resolve clashes, install per signed-off drawings

5. What it changes in practice

A clash log in the minutes, with owners and dates, moves conflicts off the site. Failure scenario: an area is released for installation before sign-off; the duct goes in first, the sprinkler main can't pass, and both trades claim extra cost.

6. Typical wording

"Clash 47 (duct vs. beam, grid C/5): mechanical to reroute; revised model by 04/08. Area not released until sign-off."

"Coordination drawings for level 2 signed off by all MEP trades 05/20; installation may proceed."

7. What to watch

  • Don't release an area before coordination sign-off.

  • Give every clash an owner and a date.

  • Check openings and sleeves before concrete is placed.

  • Protect ceiling heights and access to equipment.

  • Keep the clash log in or linked from the minutes.

  • Note who decides when trades can't agree.

8. Don't confuse with

Related term

Key difference

Submittal review

Checks one trade against the design

Clash detection

A tool within coordination, not the whole process

RFI

A question to the design team; may come out of coordination

Shop drawings

One trade's fabrication drawings

9. Related terms

Same phase: Engineering calculations, Submittal review, Drawing revision, Hold point. Same party: Consulting engineers, Architect.

Sources: AGC, MEP spatial coordination requirements for BIM · CSI MasterFormat divisions (WBDG)

Template: Design meeting minutes

<-