MEP coordination: what the Architect needs to know so a conflict is solved on paper, not on site.
OAC meeting #11. The concrete contractor places the level 1 deck. Three weeks later, the smoke exhaust duct doesn't fit: the opening was on the mechanical drawings, not on the formwork drawings. Skipped coordination is paid for with a core drill.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Coordination process | DD to construction | Architect, consultants, Contractor, MEP subcontractors | Rework, delay | Solve conflicts before installation | Coordination log, action items |
1. Definition and common mistake
MEP coordination checks that structure, ductwork, piping, conduit, sprinklers and ceilings fit together in the same space. During design, the Architect coordinates its consultants' systems. During construction, Division 01 (often Section 01 31 00) typically requires the Contractor to prepare coordination drawings or a coordinated BIM model, led by a coordinator and resolved in coordination meetings with clash detection.
Common mistake: thinking that reviewing each trade's shop drawings amounts to coordination. A drawing can conform to the design and still clash with the trade next to it.
2. When it appears
Coordination appears in OAC minutes, coordination meeting minutes, RFIs and the clash log. Variants: "coordination drawings", "clash detection", "BIM coordination", "sign-off", "sleeves and openings".
"Level 2 corridor coordination: sprinkler main lowered 4 in. to clear the duct; sign-off by all trades 05/20."
"Sleeve drawings for level 3 deck due before rebar inspection on 06/02."
3. How to read it in the minutes
If you read "coordinated" → ask who signed off, and on which drawing.
If you read a clash with no owner → assign it with a date.
If you read "field route" → coordination was skipped: check the impact on ceilings and access.
If you read "openings per MEP" → confirm they appear on the structural or formwork drawings.
4. Who does what
Party | What it means to them | What they do |
|---|---|---|
Architect | It sets ceiling heights and design intent | Answers coordination RFIs, protects clearances and access |
Consulting engineers | Their systems must fit | Resolve conflicts within design intent |
Contractor / coordinator | It runs the process | Leads coordination meetings, keeps the clash log, collects sign-offs |
MEP subcontractors | They model and install | Model their work, resolve clashes, install per signed-off drawings |
5. What it changes in practice
A clash log in the minutes, with owners and dates, moves conflicts off the site. Failure scenario: an area is released for installation before sign-off; the duct goes in first, the sprinkler main can't pass, and both trades claim extra cost.
6. Typical wording
"Clash 47 (duct vs. beam, grid C/5): mechanical to reroute; revised model by 04/08. Area not released until sign-off."
"Coordination drawings for level 2 signed off by all MEP trades 05/20; installation may proceed."
7. What to watch
Don't release an area before coordination sign-off.
Give every clash an owner and a date.
Check openings and sleeves before concrete is placed.
Protect ceiling heights and access to equipment.
Keep the clash log in or linked from the minutes.
Note who decides when trades can't agree.
8. Don't confuse with
Related term | Key difference |
|---|---|
Submittal review | Checks one trade against the design |
Clash detection | A tool within coordination, not the whole process |
RFI | A question to the design team; may come out of coordination |
Shop drawings | One trade's fabrication drawings |
9. Related terms
Same phase: Engineering calculations, Submittal review, Drawing revision, Hold point. Same party: Consulting engineers, Architect.
Sources: AGC, MEP spatial coordination requirements for BIM · CSI MasterFormat divisions (WBDG)