Mock-up

Mock-up: what the Architect needs to know so the first unit sets the standard instead of the argument.

The first bathroom is finished. The tile joints are wider than specified, the shower slope is reversed, the access panel is in the wrong wall. If nobody reviews it now, the same bathroom will be built 120 times. A mock-up or first-in-place review fixes the standard before production starts.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Quality step

Construction, before production

Architect, Contractor, trades, Owner

High

Quality, schedule

Quality items, by trade

1. Definition and common mistake

A mock-up is a sample assembly built to show materials, workmanship and interfaces before the Work proceeds: a section of façade, a typical room, a window installation. It can stand alone or be built in place. A first-in-place review checks the first finished unit of repeated work under the same logic.

Mock-ups are specified in Division 01 (Section 01 43 39 in MasterFormat) and in technical sections. Once accepted, the mock-up becomes the standard for workmanship. Under A201-2017 §3.12, samples and mock-ups don't change the Contract Documents; they show how the Work will meet them.

Common mistake: reviewing the mock-up too late, after production has already started. Every change then costs rework.

2. When it appears

In quality items before repeated work: façade, windows, bathrooms, typical units, ceilings, finishes. It comes back until accepted, then as the reference when quality is questioned. Variants: sample panel, benchmark unit, model room, first article.

Typical wording: “Bathroom mock-up, Unit 204: review 05/12 with the Architect and the Owner.” “Façade mock-up accepted with comments; remains on site until completion.”

3. How to read it in the minutes

If production starts before the mock-up is accepted → it proceeds at the Contractor's risk; record it.

If the mock-up is accepted with comments → list the comments and check them on the next units.

If a mock-up is to be demolished → confirm it can be removed only after the Work is accepted.

If the Owner wants changes after acceptance → that's a change, not a punch list item.

4. Who does what

Party

What the mock-up means to them

What they do

Contractor

The standard it will be held to

Build it early, invite the review

Architect

Design and quality check

Review, record comments, accept or reject

Owner

Look and function to confirm

Attend, decide on choices

Trades

The reference for production

Work to the accepted standard

5. What it changes in practice

An accepted mock-up ends discussions about workmanship: the answer is on site. Without it, each unit becomes a negotiation and the punch list grows.

Failure scenario: no bathroom mock-up. After 40 units, the Owner rejects the tile layout. Nothing shows what had been agreed, and rework is disputed for weeks.

6. Typical wording

“Bathroom mock-up Unit 204 accepted 05/12 with 4 comments (attached). Production may proceed.”

“Façade mock-up: sealant color rejected; new sample due 05/20. Ball in court: Contractor.”

7. What to watch

  • Schedule the mock-up before the production start date.

  • Invite the Owner when choices are at stake.

  • Record acceptance, comments and photos.

  • Keep the mock-up until the Work is accepted.

  • Treat later Owner changes as changes.

8. Don't confuse with

Related term

Key difference

Sample

A product sample, not an assembly

Submittal

Documents reviewed, not built work

Punch list

Defects at the end, not a standard at the start

Hold point

A stop before continuing, at any step

9. Related terms

Same phase (construction): Submittal review · Hold point · Punch list · Special inspection

Same party (Architect / Contractor): Changes in the Work · OAC meeting · Commissioning · Substantial Completion

<-