OAC meeting

OAC meeting: what the Architect needs to know to run a meeting whose minutes hold up months later.

Week 14 of a mid-rise project. Three action items carry over for the fourth week in a row. Nobody is sure who owns them, and the curtain wall submittal is now ten days late. The OAC meeting exists to settle exactly that: who acts, by when, on what basis. The minutes record it, and the next meeting checks it.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Meeting

Construction

Owner, Architect, Contractor

High

Traceability, schedule

Header, attendance, General Notes

1. Definition and common mistake

An OAC meeting is the regular project meeting of the Owner, the Architect and the Contractor during construction. It reviews progress, the schedule, open RFIs, submittals, changes, safety reports and coordination issues. On larger projects the Contractor's superintendent, the Owner's Rep, the CM and key subcontractors attend.

The AIA General Conditions don't create the meeting. Under AIA B101-2017 §3.6, the Architect provides Construction Phase Services. The meeting itself is usually required by Division 01, Section 01 31 19 "Project Meetings". That section sets the frequency, the attendees and who prepares and distributes the minutes. On a CM at-risk project, the CM often chairs and writes the minutes. The minutes are not Contract Documents (A201 §1.1.1).

Common mistake: treating the minutes as a place to issue directives or approve changes. The meeting coordinates; changes still go through the Contract's own instruments.

2. When it appears

The term appears in the header of the minutes ("OAC Meeting No. 14"), in Section 01 31 19 and in the Architect's agreement. Variants include "OAC", "owner's meeting", "progress meeting" and "construction progress meeting". These are different from a preconstruction conference or a subcontractor coordination meeting run by the Contractor. Typical wording:

  • "OAC Meeting No. 14, held on site, minutes prepared by the Architect."

  • "Corrections to these minutes are due within 7 days of distribution."

3. How to read it in the minutes

  • If you read "minutes prepared by the Contractor" → the Architect isn't the author: review them and send corrections in writing.

  • If you read "approved at the OAC meeting" → an approval with no instrument behind it: ask for the Change Order or the submittal review.

  • If you read "carried over" four times → the item has no owner or no due date: assign the ball in court.

  • If the attendance block lists no Owner's Rep → decisions recorded that day may need confirmation.

4. Who does what

Party

What the OAC meeting means to them

What they do

Owner

The place where it hears status and gives decisions

Sends someone authorized to decide

Architect

A Construction Phase Service under its agreement

Chairs or attends, records, distributes if Section 01 31 19 says so

Contractor

The forum to raise RFIs, delays and claims notices

Reports progress, look-ahead, open items

Subcontractors

Invited when their work is on the agenda

Attend when invited, answer action items

5. What it changes in practice

A well-run OAC meeting closes items: each one leaves with a ball in court, a due date and a status. A loosely run one produces minutes that list topics without owners. Six months later, nobody can tell who held up the work.

Failure scenario: the minutes say "structural steel connections discussed". No one is named and no date is set. The fabricator waits for an RFI response that was never formally asked. Erection slips three weeks. At the claim stage, the minutes can't show who was waiting on whom, and the Owner can't rebut the delay claim.

6. Typical wording

"Item 14.03, curtain wall shop drawings: resubmittal due Friday. Ball in court: Contractor."

"Item 12.07, closed: RFI 42 answered by the Architect, see log."

7. What to watch

  • Check who prepares the minutes under Section 01 31 19 before the first meeting.

  • Record attendance, including people who were invited but absent.

  • Give every action item a ball in court, a due date and a status.

  • Never approve a change or a submittal "at the meeting" without its own document.

  • Send corrections in writing, within the period set in the General Notes.

8. Don't confuse with

Related term

Key difference

Preconstruction conference

Held once, before work starts

Subcontractor coordination meeting

Run by the Contractor, without the Owner

Change Order

A signed contract instrument, not a meeting record

Field report