Owner: what the Architect needs to know so an Owner decision is recorded in the Owner's name.
Design meeting #7. "Accepted by the Architect: resilient flooring instead of tile in the offices." The change affects price and use. The decision belonged to the Owner, and the minutes don't say the Owner made it.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Contract party | Whole project | Owner, Owner's rep, Architect, Contractor | Program, budget, schedule | Decisions in the right name | Attendance, decisions, action items |
1. Definition and common mistake
The Owner is the party for whom the project is built and who pays for it. It defines the program and budget, hires the Architect (for example under AIA B101) and the Contractor (A101 with the A201 General Conditions), and makes decisions that change scope, price or time. A201 Article 2 sets its duties, including designating a representative with authority to bind the Owner.
Common mistake: recording an Owner decision without saying the Owner made it, or attributing it to someone without authority. What changes the program, the price or the time is an Owner decision: write it in the Owner's name, with the person and the date.
2. When it appears
The Owner appears in the attendance list, in decisions ("approved by the Owner"), in change approvals and in items awaiting an answer ("Owner to confirm"). Variants: "Owner's rep", "OR", "client", "user group", "facilities", "board".
"Owner (facilities director) approves Alternate 3; Change Order to follow."
"User group prefers sliding doors; decision pending Owner's rep by 06/10."
3. How to read it in the minutes
If you read "approved" with no name → ask who approved: the Owner, its representative or the Architect.
If you read "user group request" → users advise; the Owner decides and pays.
If you read "Owner to confirm" → put it on the action list with a date.
If you read "agreed with the client" on a cost item → a Change Order or CCD is still needed.
4. Who does what
Party | What it means to them | What they do |
|---|---|---|
Owner | It decides and pays | Approves phases, changes and payments in writing |
Owner's rep / PM | It speaks for the Owner within its authority | Confirms decisions, escalates what exceeds its authority |
Architect | It advises and records | Presents options with cost and time, writes each decision in the Owner's name |
Contractor | It acts on Owner decisions | Prices and proceeds only on written authorization |
5. What it changes in practice
Minutes that say who decided, for whom and when, survive a change of project manager or a dispute. Failure scenario: a flooring change noted as "accepted" without a name is installed. At closeout the Owner refuses the extra cost, arguing it never approved it.
6. Typical wording
"Decision 4 · The Owner (project manager) approves resilient flooring in offices 201–214, cost increase to be confirmed by Change Order. 11/24."
"Owner's rep to confirm the hardware finish by 12/01; the door schedule is on hold until then."
7. What to watch
Write the name and role of the person who decides for the Owner.
Check what the Owner's rep can approve on its own.
Separate user requests from Owner decisions.
Date every decision.
Follow every cost decision with a Change Order or CCD.
Keep the Owner in the distribution list of every set of minutes.
8. Don't confuse with
Related term | Key difference |
|---|---|
Owner's rep | Acts for the Owner within delegated authority |
User group | Advises on needs; doesn't commit money |
Architect | Advises and certifies; doesn't spend the Owner's money |
Construction manager (agency) | Advises the Owner; not the Owner |
9. Related terms
Same party: Architect, Consulting engineers, Change Order. Same phase: Design phases, Bid documents.
Sources: AIA A201–2017, Article 2 (Owner) · AIA B101–2017 summary