Purpose of meeting minutes: what the Architect needs to know so the minutes are a reliable record, not a contract by accident.
A line in the minutes says: “Owner agrees to pay for the extra steel.” The Owner says it only agreed to look at a price. Two weeks have passed and nobody corrected the minutes. Minutes record what happened in the meeting; they don't change the Contract, but an uncorrected line can still weigh in a dispute.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Principle | Construction | Architect, Contractor, Owner | High | Contract, traceability | General Notes, header |
1. Definition and common mistake
OAC meeting minutes record attendees, discussions, decisions announced, action items and status. They are prepared by the party the Contract or specifications name (often the Architect or the Contractor, per Section 01 31 19) and distributed to all parties, with a set time to request corrections.
Minutes record; they don't modify. Changes in the Work require a Change Order, a Construction Change Directive or a minor change order (A201-2017 Article 7); claims follow Article 15; notices follow the Contract's notice rules (§13.3 in A201-2017 for written notice). But minutes that go uncorrected can be used as evidence of what was said.
Common mistake: writing decisions in the minutes as if they were contract instruments, or not correcting an inaccurate line in time.
2. When it appears
In the General Notes at the top of every set of minutes: who writes them, the correction period, the fact that they don't modify the Contract. In disputes, they come back as the chronology. Variants: meeting record, OAC minutes, site meeting notes.
Typical wording: “These minutes reflect the discussions held. They do not modify the Contract Documents. Corrections must be sent in writing within 7 days of issue.”
3. How to read it in the minutes
If you read a decision with cost or time impact → check that a contract instrument follows.
If a line is wrong → correct it in writing within the period.
If the correction period isn't stated → add it to the General Notes.
If a notice is “given” in the minutes → send it by the Contract's method too.
4. Who does what
Party | What the minutes mean to them | What they do |
|---|---|---|
Author (often Architect) | The record | Write accurately, issue quickly |
Contractor | A record that may be cited | Read, correct in time |
Owner | A record of its positions | Read, correct in time |
Absent parties | Their information | Read and respond |
5. What it changes in practice
Clear General Notes and timely corrections make minutes a record everyone trusts. Without them, every line becomes a possible argument.
Failure scenario: the line “Owner agrees to pay” stays uncorrected. The Contractor bills the steel and cites the minutes. The dispute turns on why nobody objected.
6. Typical wording
“Item 12.03 corrected at the Owner's request: the Owner asked for a price; no agreement on payment.”
“Corrections to Minutes 11 received from the Contractor 05/04 and incorporated.”
7. What to watch
State the purpose and correction period in the General Notes.
Issue minutes quickly so corrections are possible.
Write facts and statements, not contract decisions.
Record corrections in the next minutes.
Send notices by the Contract's method.
8. Don't confuse with
Related term | Key difference |
|---|---|
Change Order | Changes the Contract |
Written notice | Contract-required communication |
Field report | Architect's site observations |
Daily report | Contractor's daily log |
9. Related terms