Punch list: what the Architect needs to know so every open item ends up on the list that counts.
Two weeks before turnover, the minutes carry 40 items found on walkthroughs: scuffed doors, a missing exit sign, a leaking valve. The Certificate of Substantial Completion is signed with its own list of 26. Fourteen items exist only in the minutes. The punch list is the list attached to the certificate. The minutes track its items; they don't create them.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Closeout document | Substantial Completion to final completion | Contractor, Architect, Owner | High | Contractual, financial | General Notes, closeout section |
1. Definition and common mistake
The punch list is the list of Work still to be completed or corrected when the project reaches Substantial Completion. It is the scope that stands between Substantial Completion and final completion. Its items must be finished for final payment and the release of retainage.
Under A201-2017 §9.8.2, the Contractor prepares and submits the list first. The Architect inspects (§9.8.3) and adds items. If the Work is substantially complete, the Architect prepares the Certificate of Substantial Completion with the list attached (§9.8.4; AIA form G704). The list doesn't limit the Contractor's duty to complete all the Work under the Contract Documents. The Owner may withhold, from the final payment, an amount reflecting the open items. Final completion and final payment follow §9.10.
Common mistake: treating items noted in the minutes as part of the punch list. An item missing from the certificate's list is hard to enforce later.
2. When it appears
It appears in the General Notes (closeout), in the Contractor's request for Substantial Completion inspection, in the certificate, and in closeout meetings. Variants include "punchlist", "deficiency list", "snag list" (outside the US) and "list of items to be completed or corrected". Typical wording:
"Punch list attached to the Certificate of Substantial Completion, 26 items."
"Items noted in these minutes are not the punch list."
3. How to read it in the minutes
If you read "deficiencies listed in these minutes" → move them to the Contractor's list before the inspection.
If you read a punch item with no due date → the certificate sets the time to finish it: check it.
If you read "punch list closed" with no back-check → ask for the Architect's reinspection.
If you read a punch item that is really missing scope → it may hold Substantial Completion itself.
4. Who does what
Party | What the punch list means to them | What they do |
|---|---|---|
Contractor | Work it must finish for final payment | Prepares the list, corrects, requests back-check |
Architect | A list it reviews and certifies | Inspects, adds items, attaches it to G704 |
Owner | Its leverage until final payment | Signs the certificate, withholds for open items |
Subcontractors | Items in their scope | Correct through the Contractor |
5. What it changes in practice
When everything found before turnover is moved to the Contractor's list, the certificate carries one complete list. Retainage is then released item by item. When items live only in the minutes, the Owner has less to hold them by after occupancy.
Failure scenario: a failed roof drain test is noted in the minutes, not on the list. The certificate is signed and retainage is reduced. Three months later the drain leaks into a tenant suite. The Contractor says it was never on the punch list. The Owner relies on the warranty, with a slower and costlier process.
6. Typical wording
"Items noted in these minutes are not the punch list: only the list attached to the Certificate of Substantial Completion governs."
"Punch item 14, exit sign Level 2: corrected, back-check 11/04. Ball in court: Architect."
7. What to watch
Ask the Contractor for its own list before the Substantial Completion inspection.
Move every item found on walkthroughs onto that list.
Attach the complete list to the certificate, never a partial one.
Back-check each item before you mark it closed.
Separate punch items from incomplete scope that holds Substantial Completion.
8. Don't confuse with
Related term | Key difference |
|---|---|
Action item | A meeting follow-up, not a closeout obligation |
Warranty claim | After completion, under the correction period |
Closeout submittals | Documents, not physical work |
Nonconforming work | Can be rejected at any time (A201 §12.2) |
9. Related terms
Same phase (closeout): Substantial Completion, Closeout submittals, Retainage, Certificate of Occupancy. Same party (Architect): Ball in court, Change Order, Submittal review, Application for Payment.
<-