Schedule acceptance: what the Architect needs to know so a schedule shown in a meeting doesn't become an agreement nobody meant.
The Contractor projects its updated schedule in the meeting, with a new end date six weeks later. Nobody objects; the minutes say “schedule presented”. Three months later, the Contractor argues that the new date was accepted. The minutes should say what was reviewed and what wasn't.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Contract question | Construction | Contractor, Architect, Owner | High | Schedule, liquidated damages | Schedule section |
1. Definition and common mistake
Under A201-2017 §3.10.1, the Contractor submits its schedule “for the Owner's and Architect's information”. The schedule doesn't by itself change the Contract Time; only a Change Order or other contract mechanism does. Many specifications (Section 01 32 16) add a review and acceptance step for the baseline and set response times.
Acceptance of a schedule generally means it is acceptable as a working plan, not that the Owner agrees to a later completion date or waives liquidated damages. Silence is a risk: depending on the contract and the facts, an Owner that lets a schedule stand without comment may weaken its position.
Common mistake: letting a schedule showing a late completion pass without written comment.
2. When it appears
When the baseline is submitted, at each update, and when the Contractor shows a later end date. Variants: schedule review, schedule approval, “no comments”.
Typical wording: “Update May shows Substantial Completion 10/30 vs Contract date 09/15. Owner does not accept the date change; Contract Time unchanged.” “Baseline schedule accepted as a working plan, with comments.”
3. How to read it in the minutes
If you read “schedule presented” with a later date → add the Owner's position in writing.
If the schedule is accepted → say what that acceptance covers.
If the Contractor claims time → it goes through the Contract's claim process.
If the specifications set a review time → respond within it.
4. Who does what
Party | What acceptance means to them | What they do |
|---|---|---|
Contractor | Its plan recognized | Submit, explain changes, claim time properly |
Architect | Review | Comment in writing within the set time |
Owner | Its rights on time | State its position on date changes |
5. What it changes in practice
A written position on each schedule avoids reading silence as consent. Without it, the end date drifts and liquidated damages are harder to apply.
Failure scenario: three updates with later end dates pass without comment. When the Owner applies liquidated damages, the Contractor cites the accepted schedules.
6. Typical wording
“Update May reviewed: accepted as a working plan. Completion date shown (10/30) is not accepted; Contract Time remains 09/15 unless changed by Change Order.”
“Baseline: comments due 02/20. Ball in court: Architect.”
7. What to watch
Respond to each schedule within the specified time.
Separate “working plan” from “Contract Time”.
State the Owner's position on later dates.
Route time requests to the claim process.
Keep responses with the schedule versions.
8. Don't confuse with
Related term | Key difference |
|---|---|
Change Order | Changes the Contract Time |
Baseline schedule | The reference being accepted |
Time extension | Granted under the Contract |
Liquidated damages | Depend on the Contract Time |
9. Related terms
Same phase (construction): Baseline schedule and look-ahead · Construction scheduling · Liquidated damages · Weather delay day
Same party (Owner / Architect): Change Order · Purpose of meeting minutes · OAC meeting · Ball in court
<-
BACK TO FULL GLOSSARY