Site logistics plan

Site logistics plan: what the Architect needs to know so the site layout keeps up with the job.

The crane moves for the second phase. Deliveries now block the fire lane, the laydown area sits on the future plaza's waterproofing, and the logistics plan on the trailer wall still shows the first phase. A site logistics plan is only useful if it matches the site today.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Planning document

Before mobilization, construction

Contractor, Owner, city, neighbors, Architect

Medium to high

Safety, schedule, neighbors

Site section, general items

1. Definition and common mistake

A site logistics plan is a drawing, updated by phase, that shows how the site works: fences and gates, crane location and swing radius, hoists, delivery routes, laydown and staging areas, temporary facilities, parking, pedestrian protection and fire access.

The Contractor prepares it under its control of means and methods (A201-2017 §3.3.1). Cities often require it for street use permits, crane permits and sidewalk closures. Specifications (Division 01, temporary facilities and controls) may set requirements.

Common mistake: preparing one plan at mobilization and never updating it. Each phase changes access, crane reach and storage.

2. When it appears

At mobilization, at each phase change (crane relocation, envelope closed, exterior works), and when neighbors or the city raise an issue. Variants: site plan, logistics plan, staging plan.

Typical wording: “Logistics plan phase 2 issued 06/02: crane relocated, deliveries from the north gate.” “City sidewalk permit renewal due 07/15.”

3. How to read it in the minutes

If a phase change is announced → ask for the updated logistics plan.

If storage sits on finished or protected work → ask the Contractor to move it.

If fire access or emergency routes change → confirm with the fire marshal.

If neighbors complain → check the plan's hours and routes.

4. Who does what

Party

What the plan means to them

What they do

Contractor

Its site organization

Prepare, update, enforce

Owner

Neighbors and operations

Review impacts on its activities

City

Public space

Issue permits

Architect

Design interfaces

Check protection of finished work

5. What it changes in practice

A current plan avoids conflicts between trades, deliveries and neighbors. An outdated one leaves each trade to improvise.

Failure scenario: the laydown area is placed over the plaza waterproofing without an updated plan. Leaks appear in the garage below a year later.

6. Typical wording

“Site logistics plan phase 2 rev. B issued 06/02. Info.”

“Laydown over plaza waterproofing to be relocated by 06/09. Ball in court: Contractor.”

7. What to watch

  • Update the plan at each phase change.

  • Keep fire access and emergency routes clear.

  • Protect finished work from storage and traffic.

  • Track city permits and renewals.

  • Share the plan with every new trade.

8. Don't confuse with

Related term

Key difference

Site-specific safety plan

Safety rules, not layout

Temporary facilities

Workers' facilities, part of the plan

Crane permit

City authorization

Construction schedule

Time, not space

9. Related terms

Same phase (construction): Temporary facilities · Site-specific safety plan · Area turnover · Floor release

Same party (Contractor): OAC meeting · Construction scheduling · Baseline noise survey · Benchmark

<-

BACK TO FULL GLOSSARY