Special inspection

Special inspection: what the Architect needs to know so no open discrepancy reaches the final report.

Footings, day 12. The special inspector has flagged the rebar spacing at three pads. The Contractor has corrected two and is waiting on the engineer for the third. The pour is scheduled Thursday. Special inspection is independent quality verification required by the building code. Each discrepancy has to be closed before the work is covered, and the minutes track it until then.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Code requirement

Construction, closeout

Owner, special inspector, RDP, Contractor, building official

High

Regulatory, schedule

General Notes, action items, inspection log

1. Definition and common mistake

A special inspection is an inspection of critical structural and life-safety work by an approved agency, beyond the building official's own inspections. Examples are concrete, rebar, structural steel, welding, high-strength bolting, soils and fire-resistant coatings. The inspector checks the work against the approved construction documents and reports. It doesn't approve or design anything.

IBC §1704.2 requires the owner or the owner's agent to employ the approved agency, and that agent can't be the Contractor. The registered design professional (RDP) prepares a statement of special inspections (§1704.2.3). Under §1704.2.4, discrepancies go to the Contractor first for correction. If they are not corrected, they go to the building official and the RDP. A final report documents the inspections and the correction of discrepancies. Section 1705 lists the work that requires special inspection. Many jurisdictions adopt the IBC with local amendments: check the local code.

Common mistake: writing that the inspector "approves" the work. It reports conformance; the RDP decides on deviations.

2. When it appears

It appears in the statement of special inspections, in the permit conditions, in Division 01 (Section 01 45 33 on many projects) and in the minutes when work is waiting on an inspection or a discrepancy. Variants include "special inspector", "SI", "third-party inspection", "testing and inspection agency" and "hold point". Typical wording:

  • "Discrepancy DR-14 open: rebar spacing at F-10 to F-12."

  • "No concrete placed until the special inspector confirms rebar."

3. How to read it in the minutes

  • If you read "inspector approved" → rewrite as "inspector reported conforming".

  • If you read an open discrepancy with no date → add the notice date and the ball in court.

  • If you read "engineer to review" → the RDP's written disposition closes it, not a verbal OK.

  • If you read nothing on inspections before a pour → ask whether the hold point was met.

4. Who does what

Party

What special inspection means to them

What they do

Owner

It employs the agency under IBC §1704.2

Sets reporting times in the agency's agreement

Special inspector

It verifies and reports

Reports conformance or discrepancy, issues the final report

RDP (engineer of record)

It decides on deviations from its design

Gives a written disposition

Contractor

It corrects and schedules inspections

Gives notice before work is covered, corrects discrepancies

5. What it changes in practice

When the minutes carry each discrepancy with its number, dates and ball in court, it closes before the work is covered. Left untracked, discrepancies pile up and land in the final report. The building official may then hold the certificate of occupancy.

Failure scenario: fourteen discrepancies stay open through the frame. Nobody tracked them after the field notices. At closeout, the final report lists them as uncorrected. The building official asks for engineering letters and destructive testing at two locations. Occupancy slips five weeks.

6. Typical wording

"DR-14, rebar spacing F-10 to F-12: engineer's disposition received 09/24. Ball in court: Special Inspector."

"Deck pour Level 3: hold until the special inspector confirms shear studs."

7. What to watch

  • Get the statement of special inspections before the first inspected work starts.

  • Number every discrepancy and carry it in the minutes until it is closed.

  • Ask for the RDP's disposition in writing, never a verbal OK at the meeting.

  • Confirm the reporting time set in the agency's agreement with the Owner.

  • Ask for interim reports before closeout, not only the final report.

8. Don't confuse with

Related term

Key difference

Building inspection

Done by the building official, not the Owner's agency

Structural observation

Done by the RDP on general conformance (IBC §1704.6)

Submittal review

The Architect's review of shop drawings, before fabrication

Commissioning

Verifies building systems' performance, not code conformance

9. Related terms

Same phase (construction): Hold point, Ball in court, RFI, OAC meeting. Same party (building official): AHJ, Certificate of Occupancy, Permit, Final inspection.

<-