Specifications: what the Architect needs to know so a requirement settles a difference.
OAC meeting #9. The door supplier delivers shaft doors with no fire rating. The minutes say "not per spec", with no section. The supplier answers that its product data was reviewed. A requirement has force only if someone can find it.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Contract document | CDs, procurement, construction | Architect, consultants, Contractor, subcontractors | Quality, substitutions | Cite the section | Submittals, deficiencies, RFIs |
1. Definition and common mistake
The specifications are the written requirements for materials, products, installation and quality. They sit in the Project Manual, with the procurement and contracting requirements, organized by CSI MasterFormat (Division 01 General Requirements, then technical divisions such as 08 Openings or 23 HVAC). Each section usually follows three parts: General, Products, Execution. Substitutions follow the procedure in Division 01; "or equal" doesn't mean "anything the contractor likes".
Common mistake: assuming the specifications always win over the drawings. The order of precedence, if any, is written in the contract or Division 01. That clause settles a conflict, not habit.
2. When it appears
Specifications appear in submittal reviews, deficiency lists, RFIs and substitution requests. Variants: "spec section 08 11 13", "Div. 23", "per spec", "basis of design", "or equal", "substitution request".
"Shaft doors: Section 08 11 13, 2.3.B requires a 90-minute rating. Delivered doors rejected."
"Substitution request for roofing membrane: incomplete per Section 01 25 00; returned."
3. How to read it in the minutes
If you read "not per spec" → ask for the section and paragraph.
If you read "basis of design" → other products may be acceptable if equal, through the substitution procedure.
If you read "spec and drawings conflict" → check the order of precedence clause before deciding.
If you read "reviewed" product data → the review doesn't waive a requirement unless the deviation was identified.
4. Who does what
Party | What it means to them | What they do |
|---|---|---|
Architect / spec writer | It writes the requirements | Edits sections, answers questions by section number |
Consultants | They write their divisions | Specify their systems, review related submittals |
Contractor | It must meet the requirements | Submits product data and flags deviations |
Subcontractors | They supply and install | Follow the section for their work |
5. What it changes in practice
Minutes that cite section and paragraph turn an argument into a check. Failure scenario: "not per spec" with no reference; the supplier points to a reviewed submittal, and the doors stay in place until the inspector rejects them.
6. Typical wording
"Section 08 11 13, 2.3.B: shaft doors rated 90 minutes. Delivered doors unrated: replace; reviewed submittal did not identify the deviation."
"Substitution for acoustical ceiling accepted per Section 01 25 00; Section 09 51 13 to be revised by ASI."
7. What to watch
Cite section and paragraph, not "the spec".
Check the order of precedence in the contract.
Require deviations to be identified in submittals.
Run substitutions through Division 01, in writing.
Keep specifications and drawings coordinated at each issue.
Revise the section when a substitution is accepted.
8. Don't confuse with
Related term | Key difference |
|---|---|
Drawings | Show quantity, location and relationship; specifications say quality and method |
Division 01 | General requirements for the whole project |
Product data | The manufacturer's information, submitted for review |
Standard (ASTM, UL) | Referenced by a section; binding through it |
9. Related terms
Same phase: Bid documents, Design phases, Submittal review, Drawing revision. Same party: Architect, Consulting engineers.
Sources: CSI MasterFormat divisions (WBDG) · AIA A701–2018 summary
Template: Design meeting minutes
<-