Steering Committee: what the Owner's Rep needs to know so the minutes record who decided, not just what was said.
At Steering Committee #12, the developer presented two options for docks 25 to 28, and the room agreed Option 2 “looked right.” The minutes said “Option 2 preferred.” A month later the pricing arrived, the tenant asked whether it had been approved, and nobody could point to a decision. A steering committee has decided only what its minutes record as decided, by a named person.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Governance meeting | Design through tenant delivery | Owner, owner’s rep, developer, architect, tenant | High | Decisions, budget, schedule | Decision log, open decisions, action items |
1. Definition and common mistake
A steering committee is the owner-side meeting where the people with authority over budget, scope and schedule decide what the project team cannot decide alone. The owner or its designated representative chairs it, the project manager reports, and someone records the decisions. On an AIA-based project, that authority comes from the contract: AIA A201–2017 §2.1.1 has the owner designate in writing a representative who can bind it, and the architect does not have that authority.
Common mistake: running it as a progress meeting. Progress belongs to the OAC meeting; the steering committee exists to decide.
2. When it appears
Monthly on build-to-suit and institutional projects, from design to tenant delivery. Also called owner’s meeting, executive meeting or project board. Two typical entries:
“A13-01, docks 25 to 28: decision deferred to Steering Committee #14; developer to price both options by 12/04.”
“D13-03 approved by the owner: temporary generator for testing, $20k from contingency.”
3. How to read it in the minutes
“Approved in principle” → not a decision yet. Ask who approved, for what amount, from which budget line.
“To be discussed at the next SC” → an open decision. Give it a number, a due date and a decider.
“Per the owner,” with no name → check that this person has written authority under the contract.
“Tenant agrees” → confirm it in writing if the lease requires tenant approval of changes.
4. Who does what
Party | What the steering committee means to them | What they do |
|---|---|---|
Owner | Where it commits money and scope | Decides, or delegates in writing |
Owner’s rep | The meeting it runs and records | Sets the agenda, keeps the decision log, follows up actions |
Developer | Where its proposals get approved | Brings priced options before the meeting |
Architect | Where design choices are confirmed | Flags code and design impact of each option |
Tenant | Where its requests get an answer | States requirements, accepts or declines options |
5. What it changes in practice
Minutes that number each decision and name the decider let the next meeting start from the last one, and give the lender or the tenant a clear trail. Failure scenario: a canopy is approved out loud and never logged; at delivery, landlord and tenant argue over who pays for it.
6. Typical wording
“D14-01, docks 25 to 28: Option 2 with canopy approved by the owner, $58,000 from contingency. Developer to issue the change order by 12/20.”
“A14-01, unit 3 sprinklers: open. Insurer’s review due 12/10. Decision at Steering Committee #15, by the owner after the review.”
7. What to watch
One decider per decision, named, never “the committee.”
An amount and a budget line on every approval.
Each open decision carries a due date and the meeting that will settle it.
Send the minutes within days, with a comment deadline; silence counts as approval only if the project documents say so.
Keep the steering committee separate from the OAC meeting, and link the two by decision numbers.
Record each attendee’s capacity: decision-maker, advisor, observer.
8. Don’t confuse with
Related term | Key difference |
|---|---|
OAC meeting | Owner-architect-contractor coordination; reports progress, rarely commits money |
Executive committee / investment committee | Corporate body above the project; sets the budget the SC works within |
Change order | The contract instrument; an SC decision authorizes it but does not replace it |
Owner’s representative | The person who runs the SC, not the body that decides |
9. Related terms
By phase: Baseline schedule and look-ahead · Change order · Change order request · Construction change directive. By party: Owner · Owner’s representative · Owner’s agent · Tenant and build-to-suit lease · Development agreement. → See the template: Steering committee meeting minutes.
Sources: AIA A201–2017 §2.1.1 (South Bend copy) · Ohio OBM, Steering Committee Basics.
<-