Build-to-Suit Lease: what the Owner's Rep needs to know when the tenant asks for a change.
The tenant signed a 15-year lease before the first footing was poured, with a target delivery of 06/30/2027. At Steering Committee #13, it asks for four more dock doors. Everyone agrees they make sense; nobody says who pays or whether delivery moves. In a build-to-suit, a tenant request is a lease matter first: cost, payer, delivery date and rent are settled in writing.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Lease structure | Design through tenant delivery | Owner (landlord), developer, tenant, architect | High | Delivery date, cost allocation, rent | Open decisions, tenant requests, milestones |
1. Definition and common mistake
In a build-to-suit (BTS) lease, the landlord builds a facility to one tenant’s requirements, and the tenant commits to the lease before construction starts. The lease and its work letter set the base building scope, the target delivery date, and what happens if delivery is late (rent credits, sometimes a termination right). Tenant changes after signing are priced, then billed back or folded into the rent.
Common mistake: logging a tenant request as “agreed” without its cost, its payer and its effect on the delivery date.
2. When it appears
Industrial, retail or office buildings for a single user; the minutes separate landlord’s work from tenant’s work. Two typical entries:
“Tenant request #4, docks 25 to 28: developer to price; tenant to confirm funding (bill-back or rent adjustment).”
“Target delivery 06/30/2027 confirmed; no tenant delay claimed to date.”
3. How to read it in the minutes
“Tenant approved” → check the lease’s change procedure. Is the approval signed?
“Delivery date held” → thanks to what, and is any tenant delay being claimed?
“Tenant’s work” → outside the landlord’s scope; access and sequence still need a date.
“Rent commencement” next to “delivery” → they can differ; note which one moves.
4. Who does what
Party | What the BTS lease means to them | What they do |
|---|---|---|
Owner (landlord) | The building it must deliver | Approves changes, protects the delivery date |
Developer | The scope and date it builds to | Prices tenant requests, tracks schedule impact |
Tenant | Rent from commencement | Requests, approves and funds changes |
Architect | Base building and tenant scope | Checks code and design impact |
Owner’s rep | The link between lease and construction | Logs each request with cost, payer and date impact |
5. What it changes in practice
A numbered tenant request log in the minutes ties every change to the lease. Failure scenario: four docks are built “as agreed”; the tenant refuses the bill-back, and the rent discussion reopens after delivery.
6. Typical wording
“Tenant request #4, docks 25 to 28: Option 2 with canopy, $58,000, funded from contingency by owner decision; delivery date unchanged.”
“Tenant to confirm in writing by 12/04 whether request #5 is billed back or added to rent.”
7. What to watch
Number each tenant request and keep the number across meetings.
Record who pays: landlord, tenant bill-back or rent adjustment.
Record the effect on delivery, even when it is zero.
Keep landlord’s work and tenant’s work in separate lines.
Note who speaks for the tenant: real estate, operations or project manager.
Carry the lease deadlines (delivery notice, target date) into the milestones.
8. Don’t confuse with
Related term | Key difference |
|---|---|
Tenant improvement allowance | Landlord money toward the tenant’s fit-out; a BTS builds the whole facility to spec |
Speculative building | Built without a committed tenant |
Sale-leaseback | The user owns the building, sells it, then leases it back |
Change order | The construction instrument; the tenant’s consent follows the lease |
9. Related terms
Parties: Owner · Development agreement (fee developer) · Owner’s representative. Instruments: Change order request · Change order · Baseline schedule and look-ahead · Steering committee. → See the template: Steering committee meeting minutes.
Sources: Link Logistics, Build-to-suit warehouses · NAIOP, Why build-to-suit matters more than ever (fall 2025) · Banker & Tradesman, No room for ambiguity in build-to-suit leases.
<-