Tenant and Build-to-Suit Lease

Build-to-Suit Lease: what the Owner's Rep needs to know when the tenant asks for a change.

The tenant signed a 15-year lease before the first footing was poured, with a target delivery of 06/30/2027. At Steering Committee #13, it asks for four more dock doors. Everyone agrees they make sense; nobody says who pays or whether delivery moves. In a build-to-suit, a tenant request is a lease matter first: cost, payer, delivery date and rent are settled in writing.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Lease structure

Design through tenant delivery

Owner (landlord), developer, tenant, architect

High

Delivery date, cost allocation, rent

Open decisions, tenant requests, milestones

1. Definition and common mistake

In a build-to-suit (BTS) lease, the landlord builds a facility to one tenant’s requirements, and the tenant commits to the lease before construction starts. The lease and its work letter set the base building scope, the target delivery date, and what happens if delivery is late (rent credits, sometimes a termination right). Tenant changes after signing are priced, then billed back or folded into the rent.

Common mistake: logging a tenant request as “agreed” without its cost, its payer and its effect on the delivery date.

2. When it appears

Industrial, retail or office buildings for a single user; the minutes separate landlord’s work from tenant’s work. Two typical entries:

  • “Tenant request #4, docks 25 to 28: developer to price; tenant to confirm funding (bill-back or rent adjustment).”

  • “Target delivery 06/30/2027 confirmed; no tenant delay claimed to date.”

3. How to read it in the minutes

  • “Tenant approved” → check the lease’s change procedure. Is the approval signed?

  • “Delivery date held” → thanks to what, and is any tenant delay being claimed?

  • “Tenant’s work” → outside the landlord’s scope; access and sequence still need a date.

  • “Rent commencement” next to “delivery” → they can differ; note which one moves.

4. Who does what

Party

What the BTS lease means to them

What they do

Owner (landlord)

The building it must deliver

Approves changes, protects the delivery date

Developer

The scope and date it builds to

Prices tenant requests, tracks schedule impact

Tenant

Rent from commencement

Requests, approves and funds changes

Architect

Base building and tenant scope

Checks code and design impact

Owner’s rep

The link between lease and construction

Logs each request with cost, payer and date impact

5. What it changes in practice

A numbered tenant request log in the minutes ties every change to the lease. Failure scenario: four docks are built “as agreed”; the tenant refuses the bill-back, and the rent discussion reopens after delivery.

6. Typical wording

“Tenant request #4, docks 25 to 28: Option 2 with canopy, $58,000, funded from contingency by owner decision; delivery date unchanged.”

“Tenant to confirm in writing by 12/04 whether request #5 is billed back or added to rent.”

7. What to watch

  • Number each tenant request and keep the number across meetings.

  • Record who pays: landlord, tenant bill-back or rent adjustment.

  • Record the effect on delivery, even when it is zero.

  • Keep landlord’s work and tenant’s work in separate lines.

  • Note who speaks for the tenant: real estate, operations or project manager.

  • Carry the lease deadlines (delivery notice, target date) into the milestones.

8. Don’t confuse with

Related term

Key difference

Tenant improvement allowance

Landlord money toward the tenant’s fit-out; a BTS builds the whole facility to spec

Speculative building

Built without a committed tenant

Sale-leaseback

The user owns the building, sells it, then leases it back

Change order

The construction instrument; the tenant’s consent follows the lease

9. Related terms

Parties: Owner · Development agreement (fee developer) · Owner’s representative. Instruments: Change order request · Change order · Baseline schedule and look-ahead · Steering committee. → See the template: Steering committee meeting minutes.

Sources: Link Logistics, Build-to-suit warehouses · NAIOP, Why build-to-suit matters more than ever (fall 2025) · Banker & Tradesman, No room for ambiguity in build-to-suit leases.

<-