Temporary facilities: what the Architect needs to know so workers' facilities keep pace with the crew size.
The crew doubles for finishes. There are still four portable toilets, the break trailer is full, and the handwashing station has been empty for two days. The Owner gets a complaint from a subcontractor's union representative. Temporary facilities are the Contractor's job, but the minutes show whether they were raised.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Site installation | Mobilization to demobilization | Contractor, subcontractors, Owner | Medium | Health, labor relations, schedule | Site section, logistics |
1. Definition and common mistake
Temporary facilities are the installations a site needs to run: field offices, meeting space, toilets and handwashing, drinking water, break and changing areas, first aid, temporary power, water and lighting, and storage. They appear on the site logistics plan.
The Contractor provides them under Division 01 (Section 01 50 00, temporary facilities and controls). OSHA's sanitation rules (29 CFR 1926.51) set minimum toilet counts by number of workers, drinking water and washing facilities. Some specifications also require an Owner's or Architect's field office.
Common mistake: sizing facilities for the start of the job. Crew size peaks during finishes.
2. When it appears
At mobilization (installation), at peak manpower, when facilities move because of phasing, and at demobilization. Variants: field office, site trailers, sanitary facilities, temp power.
Typical wording: “Additional toilets and handwashing station to be added for peak crew, by 05/15.” “Field office relocation to Area B for phase 2.”
3. How to read it in the minutes
If crew size increases → ask whether facilities follow.
If a complaint comes from workers → record it and ask the Contractor for a date.
If facilities move → check the logistics plan and access.
If the Owner's field office is required → check it is provided as specified.
4. Who does what
Party | What the facilities mean to them | What they do |
|---|---|---|
Contractor | Its obligation | Provide, maintain, resize |
Subcontractors | Their crews' needs | Report issues to the Contractor |
Owner | Site conditions and reputation | Follow up if complaints arise |
Architect | Observer | Record what is reported |
5. What it changes in practice
Facilities that grow with the crew avoid lost time, complaints and inspections. Undersized ones create friction that slows the whole site.
Failure scenario: facilities stay sized for 40 workers when 120 are on site. An inspection leads to a citation and a half-day stoppage while new units arrive.
6. Typical wording
“Peak crew expected 120 in June. 6 additional toilets and 2 handwashing stations by 05/30. Ball in court: Contractor.”
“Field office moved to Area B 07/01. Info.”
7. What to watch
Size facilities to peak crew, not average.
Keep them clean and supplied.
Update the logistics plan when they move.
Check required Owner and Architect spaces.
Plan demobilization before final finishes.
8. Don't confuse with
Related term | Key difference |
|---|---|
Site logistics plan | The overall layout |
Site-specific safety plan | Safety rules |
General conditions | Cost category that pays for them |
Shared site costs (France) | French cost-sharing between trades |
9. Related terms
Same phase (construction): Site logistics plan · Site-specific safety plan · Site safety orientation · Compte prorata (French term)
Same party (Contractor): OAC meeting · Action item · Ball in court · Construction scheduling
<-