TMA: a French term you'll meet in French meeting minutes, with its closest US equivalent.
On a French housing project, the minutes say: “TMA Unit B204: kitchen layout changed, plans to the plumbing trade before 03/10.” A US reader will recognize buyer options in condos or new homes, managed per unit with a cut-off date.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
French housing practice | Construction | Developer, buyers, Architect, trades | Medium | Schedule, cost, coordination | Housing section, by unit |
What it is
Travaux modificatifs acquéreurs (TMA) are changes a buyer of an off-plan home (VEFA) asks for before the work is done: partitions, finishes, plumbing locations. The developer accepts or refuses them, prices them, and sets a deadline after which no change is possible for each trade.
Closest US equivalent
Buyer options and upgrades in for-sale housing: design center selections, change requests for condo units, with cut-off dates by trade. As in France, late changes are refused or cost more.
In the minutes
TMA lines are tracked unit by unit with their status and the trades affected. The key date is the cut-off for each trade; after it, changes wait until after delivery.
Related terms
Échéancier VEFA (French term) · Changes in the Work · Submittal review · Area turnover
<-