Trade packages and delivery method: what the Architect needs to know so the minutes address the right party.
On a US job, the minutes say “Ball in court: Contractor” for everything. On a French job, they name twelve trade contractors, each under its own contract with the Owner. The structure of contracts decides who answers to whom, and the minutes have to follow it.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Contract structure | Procurement, construction | Owner, Architect, contractors, CM | High | Coordination, responsibility | General Notes, attendee list |
1. Definition and common mistake
A trade package is a portion of the work bid and awarded as a unit: concrete, curtain wall, mechanical. The delivery method decides who holds the contracts. With a general contractor (design-bid-build), one contractor holds all trades as subcontractors. With a construction manager at-risk, the CM bids trade packages and holds them. With multiple prime contracts, the Owner holds a contract with each trade, and coordination must be assigned to someone.
In France, allotissement (separate trade lots awarded directly by the Owner) is the default for public contracts. That is why French minutes address each trade directly and use a coordinator (OPC) and shared cost accounts.
Common mistake: writing minutes as if every trade had a contract with the Owner, when it is a subcontractor of the Contractor, or the reverse.
2. When it appears
In the General Notes (delivery method, who coordinates), the attendee list, and every ball in court. Variants: bid packages, scopes, multiple primes, CM at-risk, design-build.
Typical wording: “Delivery method: CM at-risk. Trade contractors are subcontractors of the CM.” “Multiple prime contracts: coordination by the Owner's construction manager.”
3. How to read it in the minutes
If a subcontractor is addressed as if contracted to the Owner → rewrite through the Contractor.
If there are multiple primes → check who coordinates and who answers for interfaces.
If a scope gap appears between packages → identify who holds it before pricing.
If French minutes are being read → each “lot” has its own contract with the Owner.
4. Who does what
Party | What the structure means to them | What they do |
|---|---|---|
Owner | Its contracts | Choose the method, assign coordination |
Architect | Contract administration | Address the right party |
Contractor / CM | Its subcontracts | Coordinate trades |
Trades | Their scope | Report through the contract holder |
5. What it changes in practice
Minutes that follow the contract structure send each request to the party that must answer. Minutes that don't create confusion over responsibility.
Failure scenario: the minutes assign a defect directly to a subcontractor. The Contractor says it never received the request; the subcontractor says it answers only to the Contractor.
6. Typical wording
“Ball in court: Contractor (curtain wall subcontractor).”
“Scope gap between roofing and sheet metal packages at parapet: CM to assign. Ball in court: CM.”
7. What to watch
State the delivery method in the General Notes.
Address requests to contract holders.
Assign coordination on multiple prime jobs.
Watch scope gaps between packages.
Adapt vocabulary when reading French minutes.
8. Don't confuse with
Related term | Key difference |
|---|---|
Subcontractor approval | Who performs, not how contracts are organized |
Construction scheduling | Coordination of time |
Compte prorata (France) | Shared costs between lots |
Design-build | One entity designs and builds |
9. Related terms