Stop-work order

Stop-work order: what the Architect needs to know so a stop is clear on who ordered it, why and until when.

The building inspector posts a stop-work order on Friday. On Monday the minutes say “site stopped”. They don't say who stopped it, on what basis, which areas, or what is needed to restart. Three weeks later, the Contractor asks for extra time and the Owner asks whose fault it was. A stop has a source and a scope, and the minutes should record both.

Type

Phase

Parties

Impact

Stake

Where in the minutes

Contract or regulatory event

Construction

Owner, Architect, Contractor, building official

High

Schedule, cost, safety

Schedule section, general items

1. Definition and common mistake

Work can stop for different reasons, each with its own rules. The Owner may order the Contractor to stop the Work when it fails to correct nonconforming work (A201-2017 §2.4). The Owner may suspend the Work for its convenience (§14.3), with an adjustment of cost and time. A building official can issue a stop-work order for code or permit issues. The Contractor's safety program, or OSHA, can stop a task for an imminent danger.

The source decides who bears the time and cost. A suspension for the Owner's convenience usually entitles the Contractor to an adjustment; a stop caused by the Contractor's nonconforming work doesn't.

Common mistake: writing “site stopped” without the source. Responsibility then becomes a debate.

2. When it appears

In the schedule section and general items: inspection failure, permit issue, safety incident, Owner funding pause, neighbor dispute. It comes back until restart, then in delay analysis. Variants: work suspension, stop order, red tag.

Typical wording: “Stop-work order posted by the building department 04/11, Level 3 framing: missing approved revision.” “Owner suspension for convenience from 05/02; restart notice to follow.”

3. How to read it in the minutes

If you read “site stopped” with no source → ask who ordered it and on what basis.

If only some areas are stopped → record which, and what continues.

If a restart condition exists → record it with its ball in court.

If time impact is claimed → the Contractor gives notice per the Contract.

4. Who does what

Party

What the stop means to them

What they do

Owner

Its own order, or one it suffers

Order in writing, or address the cause

Architect

Facts to record

Record source, scope, restart condition

Contractor

Stopped work

Secure the site, notify claims, restart when allowed

Building official

Code compliance

Post and lift the order

5. What it changes in practice

A recorded source and scope settle the time and cost question quickly. A vague “site stopped” turns into a dispute.

Failure scenario: the minutes record “stop for 2 weeks” without saying it was an Owner suspension. At closeout, the Owner applies liquidated damages for the delay; the Contractor shows the Owner's email. Nothing in the minutes helps either side.

6. Typical wording

“Building department stop-work order 04/11, Level 3 framing: approved revision missing on site. Restart after inspection. Ball in court: Contractor.”

“Owner suspension for convenience 05/02, all areas. Contractor to secure site. Info.”

7. What to watch

  • Record the source, date and scope of every stop.

  • Record what's needed to restart.

  • Separate Owner suspension from regulatory and safety stops.

  • Remind parties of the Contract's notice for time claims.

  • Record the restart date.

8. Don't confuse with

Related term

Key difference

Hold point

A planned stop before a step, not an incident

Contractor default

A failure to perform

Weather delay day

Weather stop, specific rules

Termination

The Contract ends; work doesn't resume

9. Related terms

Same phase (construction): Hold point · Weather delay day · Contractor default · Liquidated damages