Subcontractor approval: what the Architect needs to know so no subcontractor starts before the Owner had its chance to object.
A waterproofing subcontractor shows up on site. Nobody on the Owner's side knew its name. Its insurance certificate isn't on file, and the Owner had asked to review all envelope trades. The minutes should show who was proposed, when, and whether the Owner objected.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Contract procedure | Bid, construction | Contractor, Owner, Architect | Medium to high | Quality, contract, insurance | Subcontractor list, staffing section |
1. Definition and common mistake
Under A201-2017 §5.2, the Contractor furnishes, as soon as practicable after award, the names of persons or entities proposed for each principal portion of the Work. The Owner, through the Architect, may object promptly with reasonable grounds. The Contractor doesn't contract with a proposed subcontractor to which the Owner has made reasonable and timely objection. A change of subcontractor later goes through the same logic.
Public projects may add listing laws and bans on substitution after bid. The Owner may also require insurance certificates and, on public work, certified payroll.
Common mistake: treating subcontractor approval as a formality. Without a list, the Owner loses its right to object and doesn't know who is on site.
2. When it appears
After award (initial list), when a new subcontractor is proposed, and when one is replaced. Variants: subcontractor list, proposed subcontractors, sub substitution.
Typical wording: “Subcontractor list rev. 2 received 02/10; no Owner objection.” “Waterproofing subcontractor change proposed 04/03; Owner review due 04/10.”
3. How to read it in the minutes
If a new company appears on site → check it was on the list.
If the Owner objects → record it with the reason and date.
If a subcontractor is replaced mid-job → it follows the same review.
If insurance is required → record receipt of certificates.
4. Who does what
Party | What approval means to them | What they do |
|---|---|---|
Contractor | Its choice of subcontractors | Submit names, replace if objected |
Owner | Right to object | Review promptly, object with reasons |
Architect | Contract administration | Forward, record, advise |
Subcontractor | Access to the job | Provide insurance and documents |
5. What it changes in practice
A tracked list protects the Owner's right to object and keeps the site's companies known. Without it, problems surface only when something goes wrong.
Failure scenario: an unlisted subcontractor installs waterproofing. A leak appears. Its insurance lapsed months ago, and nobody had checked.
6. Typical wording
“Subcontractor list rev. 3: waterproofing changed to Company B. Owner: no objection 04/09. Info.”
“Insurance certificate for Company B due before mobilization. Ball in court: Contractor.”
7. What to watch
Get the list early and keep it current.
Record the Owner's response and date.
Check new companies on site against the list.
Collect insurance certificates before mobilization.
Apply public-project listing rules when relevant.
8. Don't confuse with
Related term | Key difference |
|---|---|
Submittal | Products and drawings, not companies |
Prequalification | Before bid, not after award |
Contractor default | Failure to perform |
Trade packages | How work is divided, not who does it |
9. Related terms