Submittal review: what the Architect needs to know so fabrication starts on reviewed documents and review times don't become delays.
The curtain wall shop drawings came back “Revise and resubmit” three weeks ago. The fabricator says it needs them in ten days to hold its slot. The Contractor says the Architect is late; the Architect says the resubmittal never came. A submittal log with dates and ball in court ends that discussion.
Type | Phase | Parties | Impact | Stake | Where in the minutes |
|---|---|---|---|---|---|
Review procedure | Construction | Contractor, subcontractors, Architect, engineers | High | Schedule, quality | Submittal log |
1. Definition and common mistake
Submittals are shop drawings, product data, samples and similar documents the Contractor provides to show how it will meet the Contract Documents (A201-2017 §3.12). The Contractor reviews and approves them first, then the Architect reviews them for the limited purpose of checking conformance with the design concept (§4.2.7). The Architect's review doesn't relieve the Contractor of its responsibility for the Work.
Section 01 33 00 sets the procedure, review times and action codes: for example “No exceptions taken”, “Make corrections noted”, “Revise and resubmit”, “Rejected”. The Contractor's submittal schedule lets the Architect plan reviews.
Common mistake: calling a reviewed submittal “approved” as if it changed the Contract. Deviations need explicit identification and, if accepted, a change.
2. When it appears
In the submittal log every meeting: due dates, received dates, review status, resubmittals, long-lead items. Variants: shop drawings, product data, samples, action submittals.
Typical wording: “Curtain wall shop drawings rev. 1: Revise and resubmit 05/02. Resubmittal due 05/12. Ball in court: Contractor.” “Elevator submittal under review, response due 05/16. Ball in court: Architect.”
3. How to read it in the minutes
If a submittal is late → check which side holds the ball.
If a long-lead item isn't submitted → raise it before it hits the schedule.
If fabrication starts before review → it proceeds at the Contractor's risk; record it.
If a deviation is hidden in a submittal → the Contractor must identify it in writing.
4. Who does what
Party | What the submittal means to them | What they do |
|---|---|---|
Contractor | Its proposal | Review, stamp, submit on schedule |
Subcontractors | Their shop drawings | Prepare through the Contractor |
Architect / engineers | Design conformance | Review within the set time, return with action |
Owner | Choices | Decide on colors and options when asked |
5. What it changes in practice
A log with dates and ball in court shows where every review stands. Without it, delays are blamed on whoever is in the room.
Failure scenario: the window submittal waits two weeks for an Owner color choice, unrecorded. The Contractor claims delay against the Architect. The log can't show who was holding it.
6. Typical wording
“Window product data: received 04/22, No exceptions taken 04/30. Info.”
“Window colors: Owner choice needed by 05/05. Ball in court: Owner.”
7. What to watch
Keep a log with received, returned and due dates.
Name the ball in court for every open submittal.
Track long-lead items separately.
Use the specified action codes, not “approved”.
Require deviations to be identified in writing.
8. Don't confuse with
Related term | Key difference |
|---|---|
RFI | A question, not a proposal |
Mock-up | Built, not on paper |
Change Order | Changes the Contract |
Closeout submittals | At the end, for the Owner's records |
9. Related terms